Operating Statistics (1)(2) Three Months Ended March 31, 2024 2023 Gold ounces produced (thousands): CC&V 28 48 Musselwhite 49 41 Porcupine 61 66 Éléonore 56 66 Red Chris (3)(4) 6 — Brucejack (3) 37 — Peñasquito 45 85 Merian 76 82 Cerro Negro 81 67 Yanacocha 91 56 Boddington 142 199 Tanami 90 63 Cadia (3) 122 — Telfer (3) 31 — Lihir (3) 181 — Ahafo 190 128 Akyem 69 71 Nevada Gold Mines (5) 264 261 Total Consolidated Newmont 1,619 1,233 Merian (25%) (19) (20) Pueblo Viejo (6) 54 60 Fruta Del Norte (3)(7) 21 — Total Attributable Newmont 1,675 1,273 Other metals produced: Red Chris copper tonnes (thousands) (3)(4) 5 — Boddington copper tonnes (thousands) 9 12 Cadia copper tonnes (thousands) (3) 21 — Telfer copper tonnes (thousands) (3) 1 — Total copper tonnes (thousands) 36 12 Peñasquito silver ounces (millions) 9 7 Peñasquito lead tonnes (thousands) 28 19 Peñasquito zinc tonnes (thousands) 58 46 (1) Gold equivalent ounces (GEOs) are calculated as pounds or ounces produced or sold multiplied by the ratio of the other metals’ price to the gold price using Gold ($1,400/oz.), Copper ($3.50/lb.), Silver ($20.00/oz.), Lead ($1.00/lb.) and Zinc ($1.20/lb.) pricing for 2024 and 2023. (2) Per unit measures may not recalculate due to rounding. (3) Sites acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (4) Newmont has a 70% interest in Red Chris, which is accounted for using the proportionate consolidation method. (5) Newmont has a 38.5% interest in Nevada Gold Mines, which is accounted for using the proportionate consolidation method. (6) Newmont has a 40% interest in Pueblo Viejo, which is accounted for as an equity method investment. (7) Newmont has a 31.9% interest in Lundin Gold, who wholly owns and operates the Fruta del Norte mine, which is accounted for as an equity method investment on a quarter lag. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 1 -- 1 of 30 -- Three Months Ended March 31, 2024 2023 Gold ounces sold (thousands): CC&V 29 48 Musselwhite 49 44 Porcupine 61 65 Éléonore 56 68 Red Chris (1)(2) 7 — Brucejack (1) 34 — Peñasquito 44 56 Merian 74 83 Cerro Negro 74 61 Yanacocha 90 53 Boddington 142 198 Tanami 91 65 Cadia (1) 114 — Telfer (1) 26 — Lihir (1) 182 — Ahafo 184 131 Akyem 75 78 Nevada Gold Mines (3) 267 258 Total Consolidated Newmont 1,599 1,208 Merian (25%) (18) (20) Total Attributable Newmont 1,581 1,188 Other metals sold: Red Chris copper tonnes (thousands) (1)(2) 6 — Boddington copper tonnes (thousands) 9 12 Cadia copper tonnes (thousands) (1) 20 — Telfer copper tonnes (thousands) (1) 1 — Total copper tonnes (thousands) 36 12 Peñasquito silver ounces (millions) 10 6 Peñasquito lead tonnes (thousands) 29 17 Peñasquito zinc tonnes (thousands) 61 45 (1) Sites acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Newmont has a 70% interest in Red Chris, which is accounted for using the proportionate consolidation method. (3) Newmont has a 38.5% interest in Nevada Gold Mines, which is accounted for using the proportionate consolidation method. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 2 -- 2 of 30 -- CAS (1)(2) Three Months Ended March 31, 2024 2023 Gold Costs Applicable to Sales ($/ounce) CC&V $ 1,394 $ 1,062 Musselwhite $ 1,175 $ 1,313 Porcupine $ 1,042 $ 1,071 Éléonore $ 1,441 $ 1,095 Red Chris (3) $ 940 $ — Brucejack (3) $ 2,175 $ — Peñasquito $ 853 $ 1,199 Merian $ 1,221 $ 1,028 Cerro Negro $ 861 $ 1,146 Yanacocha $ 972 $ 1,067 Boddington $ 1,016 $ 841 Tanami $ 902 $ 936 Cadia (3) $ 648 $ — Telfer (3) $ 2,632 $ — Lihir (3) $ 936 $ — Ahafo $ 865 $ 992 Akyem $ 1,006 $ 810 Nevada Gold Mines $ 1,177 $ 1,109 Total Newmont - Gold $ 1,057 $ 1,025 Co-product GEO Costs Applicable to Sales ($/GEO) Red Chris (3) $ 1,011 $ — Peñasquito $ 843 $ 954 Boddington $ 942 $ 809 Cadia (3) $ 594 $ — Telfer (3) $ 2,882 $ — Total Newmont - Co-product GEO $ 829 $ 918 Co-product by metal Costs Applicable to Sales ($/unit) Red Chris - copper ($/tonne) (3) $ 5,571 $ — Boddington - copper ($/tonne) $ 5,192 $ 4,461 Cadia - copper ($/tonne) (3) $ 3,271 $ — Telfer - copper ($/tonne) (3) $ 15,885 $ — Total Copper CAS ($/tonne) $ 4,452 $ 4,461 Peñasquito - silver ($/oz) $ 11 $ 13 Peñasquito - lead ($/tonne) $ 1,215 $ 1,325 Peñasquito - zinc ($/tonne) $ 1,764 $ 1,900 (1) Costs applicable to sales (CAS) per unit, included at the consolidated and site level, are non-GAAP metrics and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. For reconciliation of non-GAAP metrics, please see Newmont’s website or filings, available at https://www.newmont.com/about/document-library/ or http://www.sec.gov. (2) Consolidated CAS excludes Depreciation and amortization and Reclamation and remediation. (3) Sites acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 3 -- 3 of 30 -- AISC (1) Three Months Ended March 31, 2024 2023 Gold All-In Sustaining Costs ($/ounce) CC&V $ 1,735 $ 1,375 Musselwhite $ 1,766 $ 1,681 Porcupine $ 1,470 $ 1,412 Éléonore $ 1,920 $ 1,420 Red Chris (2) $ 1,277 $ — Brucejack (2) $ 2,580 $ — Peñasquito $ 1,079 $ 1,539 Merian $ 1,530 $ 1,235 Cerro Negro $ 1,120 $ 1,379 Yanacocha $ 1,123 $ 1,332 Boddington $ 1,242 $ 1,035 Tanami $ 1,149 $ 1,219 Cadia (2) $ 989 $ — Telfer (2) $ 3,017 $ — Lihir (2) $ 1,256 $ — Ahafo $ 1,010 $ 1,366 Akyem $ 1,254 $ 1,067 Nevada Gold Mines $ 1,576 $ 1,405 Total Newmont $ 1,439 $ 1,376 Co-product GEO All-In Sustaining Costs ($/GEO) Red Chris (2) $ 1,400 $ — Peñasquito $ 1,102 $ 1,351 Boddington $ 1,081 $ 1,019 Cadia (2) $ 1,027 $ — Telfer (2) $ 3,745 $ — Total Newmont $ 1,148 $ 1,322 Co-product by metal All-In Sustaining Costs ($/unit) Red Chris - copper ($/tonne) (2) $ 7,718 $ — Boddington - copper ($/tonne) $ 5,959 $ 5,616 Cadia - copper ($/tonne) (2) $ 5,659 $ — Telfer - copper ($/tonne) (2) $ 20,643 $ — Total Copper AISC ($/tonne) $ 6,392 $ 5,921 Peñasquito - silver ($/oz) $ 15 $ 18 Peñasquito - lead ($/tonne) $ 1,500 $ 1,699 Peñasquito - zinc ($/tonne) $ 2,368 $ 2,856 (1) All-in sustaining costs (AISC) per unit, included at the consolidated and site level, is a non-GAAP metric and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. For reconciliation of non-GAAP metrics, please see Newmont’s website or filings, available at https://www.newmont.com/about/document-library/ or http://www.sec.gov. (2) Sites acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 4 -- 4 of 30 -- CAPITAL EXPENDITURES Three Months Ended March 31, 2024 2023 Consolidated Capital Expenditures ($ millions) CC&V $ 5 $ 10 Musselwhite 26 14 Porcupine 40 22 Éléonore 21 14 Red Chris (1)(2) 35 — Brucejack (1) 16 — Peñasquito 32 35 Merian 18 14 Cerro Negro 46 35 Yanacocha 24 63 Boddington 28 37 Tanami 85 74 Cadia (1) 111 — Telfer (1) 10 — Lihir (1) 55 — Ahafo 90 90 Akyem 9 10 Nevada Gold Mines (3) 118 84 Corporate and other 4 6 Accrual basis $ 773 $ 508 Decrease (increase) in non-cash adjustments 77 18 Cash basis $ 850 $ 526 (1) Sites acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Newmont has a 70% interest in Red Chris, which is accounted for using the proportionate consolidation method. (3) Newmont has a 38.5% interest in Nevada Gold Mines, which is accounted for using the proportionate consolidation method. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 5 -- 5 of 30 -- CC&V Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 5,388 5,790 Open pit waste 3,423 3,500 Total open pit 8,811 9,290 Tons milled/processed (000 tonnes): Leach 5,286 5,755 Average ore grade (g/tonne): Leach 0.460 0.416 Gold produced (koz): Consolidated/Attributable 28 48 Gold sold (koz): Consolidated/Attributable 29 48 Gold production costs ($M): Costs applicable to sales (1) $ 40 $ 51 Depreciation and amortization $ 3 $ 7 Reclamation accretion $ 3 $ 2 Gold production costs (per oz sold): Direct mining and production costs $ 1,883 $ 1,179 By-product credits (8) (13) Royalties and production taxes 136 87 Inventory change, write-downs, and other (617) (191) Costs applicable to sales (per oz sold) (1) $ 1,394 $ 1,062 Depreciation and amortization $ 119 $ 153 Reclamation accretion $ 95 $ 52 All-in sustaining costs (per oz sold) $ 1,735 $ 1,375 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 6 -- 6 of 30 -- MUSSELWHITE Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes) 255 253 Tons milled/processed (000 tonnes): Mill 255 254 Average ore grade (g/tonne): Mill 6.129 5.337 Average mill recovery rate 95.7 % 95.5 % Gold produced (koz): Consolidated/Attributable 49 41 Gold sold (koz): Consolidated/Attributable 49 44 Gold production costs ($M): Costs applicable to sales (1) $ 57 $ 58 Depreciation and amortization $ 18 $ 19 Reclamation accretion $ 1 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 1,094 $ 1,275 By-product credits (3) (2) Royalties and production taxes 42 44 Inventory change, write-downs, and other 42 (4) Costs applicable to sales (per oz sold) (1) $ 1,175 $ 1,313 Depreciation and amortization $ 367 $ 429 Reclamation accretion $ 17 $ 18 All-in sustaining costs (per oz sold) $ 1,766 $ 1,681 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 7 -- 7 of 30 -- PORCUPINE Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 243 860 Open pit waste 324 1,460 Total open pit 567 2,320 Total underground ore (000 tonnes) 221 221 Tons milled/processed (000 tonnes): Mill 698 664 Average ore grade milled (g/tonne): Mill 2.925 3.281 Average mill recovery rate 91.5 % 91.9 % Gold produced (koz): Consolidated/Attributable 61 66 Gold sold (koz): Consolidated/Attributable 61 65 Gold production costs ($M): Costs applicable to sales (1) $ 63 $ 70 Depreciation and amortization $ 23 $ 29 Reclamation accretion $ 2 $ 2 Gold production costs (per oz sold): Direct mining and production costs $ 1,198 $ 1,185 By-product credits (4) (4) Royalties and production taxes 45 23 Inventory change, write-downs, and other (197) (132) Costs applicable to sales (per oz sold) (1) $ 1,042 $ 1,071 Depreciation and amortization $ 378 $ 454 Reclamation accretion $ 38 $ 32 All-in sustaining costs (per oz sold) $ 1,470 $ 1,412 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 8 -- 8 of 30 -- ÉLÉONORE Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes) 461 450 Tons milled/processed (000 tonnes): Mill 460 450 Average ore grade (g/tonne): Mill 4.286 5.059 Average mill recovery rate 90.9 % 90.7 % Gold produced (koz): Consolidated/Attributable 56 66 Gold sold (koz): Consolidated/Attributable 56 68 Gold production costs ($M): Costs applicable to sales (1) $ 80 $ 75 Depreciation and amortization $ 19 $ 27 Reclamation accretion $ 1 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 1,474 $ 1,049 By-product credits (2) (1) Royalties and production taxes 50 43 Inventory change, write-downs, and other (81) 4 Costs applicable to sales (per oz sold) (1) $ 1,441 $ 1,095 Depreciation and amortization $ 348 $ 392 Reclamation accretion $ 17 $ 11 All-in sustaining costs (per oz sold) $ 1,920 $ 1,420 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 9 -- 9 of 30 -- RED CHRIS - GOLD (1)(2) Three Months Ended March 31, 2024 2023 Open pit tonnes mined (000 tonnes): Open pit ore 2,608 — Open pit waste 2,977 — Total open pit 5,585 — Tonnes milled/processed (000 tonnes): Mill 1,470 — Average ore grade (g/tonne): Mill 0.263 — Average mill recovery rate 53.6 % — % Gold produced (koz): Consolidated/Attributable 6 — Gold sold (koz): Consolidated/Attributable 7 — Gold production costs ($M): Costs applicable to sales (3) $ 7 $ — Depreciation and amortization $ 2 $ — Reclamation accretion $ — $ — Gold production costs (per oz sold): Direct mining and production costs $ 1,428 $ — By-product credits (4) — Royalties and production taxes 28 — Inventory change, write-downs, and other (512) — Costs applicable to sales (per oz sold) (3) $ 940 $ — Depreciation and amortization $ 244 $ — Reclamation accretion $ 12 $ — All-in sustaining costs (per oz sold) $ 1,277 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Newmont has a 70% interest in Red Chris, which is accounted for using the proportionate consolidation method. (3) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 10 -- 10 of 30 -- RED CHRIS - COPPER (1)(2) Three Months Ended March 31, 2024 2023 Open pit tonnes mined (000 tonnes): Open pit ore 2,608 — Open pit waste 2,977 — Total open pit 5,585 — Tonnes milled/processed (000 tonnes): Mill 1,470 — Average ore grade: Mill 0.43 % — % Average mill recovery rate 83.4 % — % Copper produced (ktonne): Consolidated/Attributable 5 — Copper sold (ktonne): Consolidated/Attributable 6 — Co-product GEO produced (k): Consolidated/Attributable 28 — Co-product GEO sold (k): Consolidated/Attributable 31 — Co-product production costs ($M): Costs applicable to sales (3) $ 31 $ — Depreciation and amortization $ 8 $ — Reclamation accretion $ — $ — Copper production costs (per tonne sold): Direct mining and production costs $ 8,463 $ — By-product credits (22) — Royalties and production taxes 166 — Inventory change, write-downs, and other (3,036) — Costs applicable to sales (per tonne sold) (3) $ 5,571 $ — Depreciation and amortization $ 1,444 $ — Reclamation accretion $ 74 $ — All-in sustaining costs (per tonne sold) $ 7,718 $ — Copper production costs (per GEO sold): Direct mining and production costs $ 1,536 $ — By-product credits (4) — Royalties and production taxes 30 — Inventory change, write-downs, and other (551) — Costs applicable to sales (per GEO sold) (3) $ 1,011 $ — Depreciation and amortization $ 262 $ — Reclamation accretion $ 13 $ — All-in sustaining costs (per GEO sold) $ 1,400 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Newmont has a 70% interest in Red Chris, which is accounted for using the proportionate consolidation method. (3) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 11 -- 11 of 30 -- BRUCEJACK (1) Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes) 231 — Tonnes milled/processed (000 tonnes): Mill 221 — Average ore grade (g/tonne): Mill 5.512 — Average mill recovery rate 95.9 % — % Gold produced (koz): Consolidated/Attributable 37 — Gold sold (koz): Consolidated/Attributable 34 — Gold production costs ($M): Costs applicable to sales (2) $ 74 $ — Depreciation and amortization $ 35 $ — Reclamation accretion $ 1 $ — Gold production costs (per oz sold): Direct mining and production costs $ 2,284 $ — By-product credits (26) — Royalties and production taxes 32 — Inventory change, write-downs, and other (115) — Costs applicable to sales (per oz sold) (2) $ 2,175 $ — Depreciation and amortization $ 1,045 $ — Reclamation accretion $ 15 $ — All-in sustaining costs (per oz sold) $ 2,580 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 12 -- 12 of 30 -- PEÑASQUITO - GOLD Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 10,695 9,926 Open pit waste 26,879 33,858 Total open pit 37,574 43,784 Tons milled/processed (000 tonnes): Mill 7,882 9,283 Average ore grade (g/tonne): Mill 0.384 0.501 Average mill recovery rate 53.4 % 62.7 % Gold produced (koz): Consolidated/Attributable 45 85 Gold sold (koz): Consolidated/Attributable 44 56 Gold production costs ($M): Costs applicable to sales (1) $ 38 $ 67 Depreciation and amortization $ 15 $ 20 Reclamation accretion $ 1 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 832 $ 1,437 By-product credits (9) (7) Royalties and production taxes 33 42 Inventory change, write-downs, and other (3) (273) Costs applicable to sales (per oz sold) (1) $ 853 $ 1,199 Depreciation and amortization $ 334 $ 367 Reclamation accretion $ 16 $ 22 All-in sustaining costs (per oz sold) $ 1,079 $ 1,539 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 13 -- 13 of 30 -- PEÑASQUITO - SILVER Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 10,695 9,926 Open pit waste 26,879 33,858 Total open pit 37,574 43,784 Tons milled/processed (000 tonnes): Mill 7,882 9,283 Average ore grade (g/tonne): Mill 50.590 34.120 Average mill recovery rate 82.5 % 81.6 % Silver produced (Moz): Consolidated/Attributable 9 7 Silver sold (Moz): Consolidated/Attributable 10 6 Co-product production costs ($M): Costs applicable to sales (1) $ 255 $ 190 Depreciation and amortization $ 94 $ 56 Reclamation accretion $ 4 $ 3 Silver production costs (per oz sold): Direct mining and production costs $ 11 $ 16 By-product credits — — Royalties and production taxes — — Inventory change, write-downs, and other — (3) Costs applicable to sales (per oz sold) (1) $ 11 $ 13 Depreciation and amortization $ 4 $ 4 Reclamation accretion $ — $ — All-in sustaining costs (per oz sold) $ 15 $ 18 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 14 -- 14 of 30 -- PEÑASQUITO - ZINC Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 10,695 9,926 Open pit waste 26,879 33,858 Total open pit 37,574 43,784 Tons milled/processed (000 tonnes): Mill 7,882 9,283 Average ore grade: Mill 1.05 % 0.76 % Average mill recovery rate 82.4 % 79.7 % Zinc produced (ktonne): Consolidated/Attributable 58 46 Zinc sold (ktonne): Consolidated/Attributable 61 45 Co-product production costs ($M): Costs applicable to sales (1) $ 255 $ 190 Depreciation and amortization $ 94 $ 56 Reclamation accretion $ 4 $ 3 Zinc production costs (per tonne sold): Direct mining and production costs $ 1,668 $ 2,018 By-product credits (16) (9) Royalties and production taxes 57 54 Inventory change, write-downs, and other 55 (163) Costs applicable to sales (per tonne sold) (1) $ 1,764 $ 1,900 Depreciation and amortization $ 586 $ 530 Reclamation accretion $ 27 $ 28 All-in sustaining costs (per tonne sold) $ 2,368 $ 2,856 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 15 -- 15 of 30 -- PEÑASQUITO - LEAD Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 10,695 9,926 Open pit waste 26,879 33,858 Total open pit 37,574 43,784 Tons milled/processed (000 tonnes): Mill 7,882 9,283 Average ore grade: Mill 0.51 % 0.31 % Average mill recovery rate 73.7 % 70.0 % Lead produced (ktonne): Consolidated/Attributable 28 19 Lead sold (ktonne): Consolidated/Attributable 29 17 Co-product production costs ($M): Costs applicable to sales (1) $ 255 $ 190 Depreciation and amortization $ 94 $ 56 Reclamation accretion $ 4 $ 3 Lead production costs (per tonne sold): Direct mining and production costs $ 1,191 $ 1,664 By-product credits (13) (8) Royalties and production taxes 48 49 Inventory change, write-downs, and other (11) (380) Costs applicable to sales (per tonne sold) (1) $ 1,215 $ 1,325 Depreciation and amortization $ 487 $ 406 Reclamation accretion $ 23 $ 26 All-in sustaining costs (per tonne sold) $ 1,500 $ 1,699 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 16 -- 16 of 30 -- PEÑASQUITO - CO-PRODUCT GEO Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 10,695 9,926 Open pit waste 26,879 33,858 Total open pit 37,574 43,784 Tons milled/processed (000 tonnes): Mill 7,882 9,283 Average ore grade milled: Silver (g/tonne) 50.590 34.120 Zinc 1.05 % 0.76 % Lead 0.51 % 0.31 % Average mill recovery rate: Silver 82.5 % 81.6 % Zinc 82.4 % 79.7 % Lead 73.7 % 70.0 % Co-product GEO produced (k): Consolidated/Attributable 288 224 Co-product GEO sold (k): Consolidated/Attributable 303 199 Co-product production costs ($M): Costs applicable to sales (1) $ 255 $ 190 Depreciation and amortization $ 94 $ 56 Reclamation accretion $ 4 $ 3 Co-product production costs (per GEO sold): Direct mining and production costs $ 813 $ 1,099 By-product credits (8) (5) Royalties and production taxes 30 31 Inventory change, write-downs, and other 8 (171) Costs applicable to sales (per GEO sold) (1) $ 843 $ 954 Depreciation and amortization $ 311 $ 280 Reclamation accretion $ 14 $ 16 All-in sustaining costs (per GEO sold) $ 1,102 $ 1,351 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 17 -- 17 of 30 -- MERIAN Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 3,005 1,747 Open pit waste 11,776 5,989 Total open pit 14,781 7,736 Tons milled/processed (000 tonnes): Mill 3,820 3,396 Average ore grade (g/tonne): Mill 0.644 0.766 Average mill recovery rate 91.8 % 93.0 % Gold produced (koz): Consolidated 76 82 Attributable 57 62 Gold sold (koz): Consolidated 74 83 Attributable 56 63 Gold production costs ($M): Costs applicable to sales (1) $ 90 $ 85 Depreciation and amortization $ 19 $ 18 Reclamation accretion $ 1 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 1,148 $ 978 By-product credits (1) (1) Royalties and production taxes 125 113 Inventory change, write-downs, and other (51) (62) Costs applicable to sales (per oz sold) (1) $ 1,221 $ 1,028 Depreciation and amortization $ 263 $ 212 Reclamation accretion $ 15 $ 9 All-in sustaining costs (per oz sold) $ 1,530 $ 1,235 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 18 -- 18 of 30 -- CERRO NEGRO Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes) 267 293 Tons milled/processed (000 tonnes): Mill 264 298 Average ore grade (g/tonne): Mill 9.900 7.523 Average mill recovery rate 95.0 % 93.5 % Gold produced (koz): Consolidated/Attributable 81 67 Gold sold (koz): Consolidated/Attributable 74 61 Gold production costs ($M): Costs applicable to sales (1) $ 63 $ 70 Depreciation and amortization $ 30 $ 31 Reclamation accretion $ 1 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 952 $ 1,259 By-product credits (90) (135) Royalties and production taxes 107 90 Inventory change, write-downs, and other (108) (68) Costs applicable to sales (per oz sold) (1) $ 861 $ 1,146 Depreciation and amortization $ 400 $ 507 Reclamation accretion $ 15 $ 15 All-in sustaining costs (per oz sold) $ 1,120 $ 1,379 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 19 -- 19 of 30 -- YANACOCHA Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 3,500 4,857 Open pit waste 9,065 9,703 Total open pit 12,565 14,560 Tons milled/processed (000 tonnes): Leach 3,500 4,857 Average ore grade (g/tonne): Leach 0.540 0.610 Gold produced (koz): Consolidated/Attributable 91 56 Gold sold (koz): Consolidated/Attributable 90 53 Gold production costs ($M): Costs applicable to sales (1) $ 88 $ 56 Depreciation and amortization $ 28 $ 16 Reclamation accretion $ 2 $ 1 Gold production costs (per oz sold): Direct mining and production costs $ 741 $ 1,324 By-product credits (11) (15) Royalties and production taxes 62 59 Inventory change, write-downs, and other 180 (301) Costs applicable to sales (per oz sold) (1) $ 972 $ 1,067 Depreciation and amortization $ 308 $ 295 Reclamation accretion $ 21 $ 26 All-in sustaining costs (per oz sold) $ 1,123 $ 1,332 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 20 -- 20 of 30 -- BODDINGTON - GOLD Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 6,054 8,239 Open pit waste 11,769 6,266 Total open pit 17,823 14,505 Tons milled/processed (000 tonnes): Mill 8,420 9,143 Average ore grade (g/tonne): Mill 0.614 0.794 Average mill recovery rate 85.9 % 86.5 % Gold produced (koz): Consolidated/Attributable 142 199 Gold sold (koz): Consolidated/Attributable 142 198 Gold production costs ($M): Costs applicable to sales (1) $ 144 $ 167 Depreciation and amortization $ 26 $ 28 Reclamation accretion $ 2 $ 2 Gold production costs (per oz sold): Direct mining and production costs $ 1,112 $ 809 By-product credits (19) (17) Royalties and production taxes 52 46 Inventory change, write-downs, and other (129) 3 Costs applicable to sales (per oz sold) (1) $ 1,016 $ 841 Depreciation and amortization $ 181 $ 141 Reclamation accretion $ 17 $ 11 All-in sustaining costs (per oz sold) $ 1,242 $ 1,035 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 21 -- 21 of 30 -- BODDINGTON - COPPER Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 6,054 8,239 Open pit waste 11,769 6,266 Total open pit 17,823 14,505 Tons milled/processed (000 tonnes): Mill 8,420 9,143 Average ore grade: Mill 0.13 % 0.16 % Average mill recovery rate 83.5 % 82.8 % Copper produced (ktonne): Consolidated/Attributable 9 12 Copper sold (ktonne): Consolidated/Attributable 9 12 Co-product GEO produced (k): Consolidated/Attributable 49 64 Co-product GEO sold (k): Consolidated/Attributable 51 66 Co-product production costs ($M): Costs applicable to sales (1) $ 48 $ 53 Depreciation and amortization $ 9 $ 9 Reclamation accretion $ 1 $ 1 Copper production costs (per tonne sold): Direct mining and production costs $ 5,659 $ 4,116 By-product credits (101) (90) Royalties and production taxes 363 416 Inventory change, write-downs, and other (729) 19 Costs applicable to sales (per tonne sold) (1) $ 5,192 $ 4,461 Depreciation and amortization $ 967 $ 761 Reclamation accretion $ 89 $ 60 All-in sustaining costs (per tonne sold) $ 5,959 $ 5,616 Copper production costs (per GEO sold): Direct mining and production costs $ 1,026 $ 746 By-product credits (18) (16) Royalties and production taxes 66 75 Inventory change, write-downs, and other (132) 4 Costs applicable to sales (per GEO sold) (1) $ 942 $ 809 Depreciation and amortization $ 175 $ 138 Reclamation accretion $ 16 $ 11 All-in sustaining costs (per GEO sold) $ 1,081 $ 1,019 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 22 -- 22 of 30 -- TANAMI Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes) 632 554 Tons milled/processed (000 tonnes): Mill 528 389 Average ore grade (g/tonne): Mill 5.273 5.274 Average mill recovery rate 98.7 % 98.0 % Gold produced (koz): Consolidated/Attributable 90 63 Gold sold (koz): Consolidated/Attributable 91 65 Gold production costs ($M): Costs applicable to sales (1) $ 82 $ 61 Depreciation and amortization $ 25 $ 19 Reclamation accretion $ 1 $ — Gold production costs (per oz sold): Direct mining and production costs $ 987 $ 1,185 By-product credits (2) (2) Royalties and production taxes 53 50 Inventory change, write-downs, and other (136) (297) Costs applicable to sales (per oz sold) (1) $ 902 $ 936 Depreciation and amortization $ 276 $ 294 Reclamation accretion $ 6 $ 7 All-in sustaining costs (per oz sold) $ 1,149 $ 1,219 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 23 -- 23 of 30 -- CADIA - GOLD (1) Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes): 7,154 — Tonnes milled/processed (000 tonnes): Mill 7,157 — Average ore grade (g/tonne): Mill 0.678 — Average mill recovery rate 79.8 % — % Gold produced (koz): Consolidated/Attributable 122 — Gold sold (koz): Consolidated/Attributable 114 — Gold production costs ($M): Costs applicable to sales (2) $ 74 $ — Depreciation and amortization $ 28 $ — Reclamation accretion $ — $ — Gold production costs (per oz sold): Direct mining and production costs $ 647 $ — By-product credits (103) — Royalties and production taxes 74 — Inventory change, write-downs, and other 30 — Costs applicable to sales (per oz sold) (2) $ 648 $ — Depreciation and amortization $ 246 $ — Reclamation accretion $ 3 $ — All-in sustaining costs (per oz sold) $ 989 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 24 -- 24 of 30 -- CADIA - COPPER (1) Three Months Ended March 31, 2024 2023 Total underground ore (000 tonnes): 7,154 — Tonnes milled/processed (000 tonnes): Mill 7,157 — Average ore grade: Mill 0.37 % — % Average mill recovery rate 84.6 % — % Copper produced (ktonne): Consolidated/Attributable 21 — Copper sold (ktonne): Consolidated/Attributable 20 — Co-product GEO produced (k): Consolidated/Attributable 118 — Co-product GEO sold (k): Consolidated/Attributable 112 — Co-product production costs ($M): Costs applicable to sales (2) $ 67 $ — Depreciation and amortization $ 27 $ — Reclamation accretion $ — $ — Copper production costs (per tonne sold): Direct mining and production costs $ 3,345 $ — By-product credits (559) — Royalties and production taxes 307 — Inventory change, write-downs, and other 178 — Costs applicable to sales (per tonne sold) (2) $ 3,271 $ — Depreciation and amortization $ 1,332 $ — Reclamation accretion $ 18 $ — All-in sustaining costs (per tonne sold) $ 5,659 $ — Copper production costs (per GEO sold): Direct mining and production costs $ 607 $ — By-product credits (101) — Royalties and production taxes 56 — Inventory change, write-downs, and other 32 — Costs applicable to sales (per GEO sold) (2) $ 594 $ — Depreciation and amortization $ 242 $ — Reclamation accretion $ 3 $ — All-in sustaining costs (per GEO sold) $ 1,027 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 25 -- 25 of 30 -- TELFER - GOLD (1) Three Months Ended March 31, 2024 2023 Open pit tonnes mined (000 tonnes): Open pit ore 3,268 — Open pit waste 4,997 — Total open pit 8,265 — Total underground ore (000 tonnes): 238 — Tonnes milled/processed (000 tonnes): Mill 1,375 — Average ore grade (g/tonne): Mill 0.892 — Average mill recovery rate 87.9 % — % Gold produced (koz): Consolidated/Attributable 31 — Gold sold (koz): Consolidated/Attributable 26 — Gold production costs ($M): Costs applicable to sales (2) $ 70 $ — Depreciation and amortization $ 8 $ — Reclamation accretion $ 2 $ — Gold production costs (per oz sold): Direct mining and production costs $ 3,975 $ — By-product credits (7) — Royalties and production taxes 54 — Inventory change, write-downs, and other (1,390) — Costs applicable to sales (per oz sold) (2) $ 2,632 $ — Depreciation and amortization $ 303 $ — Reclamation accretion $ 83 $ — All-in sustaining costs (per oz sold) $ 3,017 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 26 -- 26 of 30 -- TELFER - COPPER (1) Three Months Ended March 31, 2024 2023 Open pit tonnes mined (000 tonnes): Open pit ore 3,268 — Open pit waste 4,997 — Total open pit 8,265 — Total underground ore (000 tonnes): 238 — Tonnes milled/processed (000 tonnes): Mill 1,375 — Average ore grade: Mill 0.11 % — % Average mill recovery rate 78.2 % — % Copper produced (ktonne): Consolidated/Attributable 1 — Copper sold (ktonne): Consolidated/Attributable 1 — Co-product GEO produced (k): Consolidated/Attributable 6 — Co-product GEO sold (k): Consolidated/Attributable 5 — Co-product production costs ($M): Costs applicable to sales (2) $ 15 $ — Depreciation and amortization $ 2 $ — Reclamation accretion $ — $ — Copper production costs (per tonne sold): Direct mining and production costs $ 22,727 $ — By-product credits (41) — Royalties and production taxes 318 — Inventory change, write-downs, and other (7,119) — Costs applicable to sales (per tonne sold) (2) $ 15,885 $ — Depreciation and amortization $ 1,951 $ — Reclamation accretion $ 476 $ — All-in sustaining costs (per tonne sold) $ 20,643 $ — Copper production costs (per GEO sold): Direct mining and production costs $ 4,124 $ — By-product credits (8) — Royalties and production taxes 58 — Inventory change, write-downs, and other (1,292) — Costs applicable to sales (per GEO sold) (2) $ 2,882 $ — Depreciation and amortization $ 354 $ — Reclamation accretion $ 86 $ — All-in sustaining costs (per GEO sold) $ 3,745 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 27 -- 27 of 30 -- LIHIR (1) Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 2,555 — Open pit waste 6,955 — Total open pit 9,510 — Tonnes milled/processed (000 tonnes): Mill 2,871 — Average ore grade (g/tonne): Mill 2.500 — Average mill recovery rate 75.6 % — % Gold produced (koz): Consolidated/Attributable 181 — Gold sold (koz): Consolidated/Attributable 182 — Gold production costs ($M): Costs applicable to sales (2) $ 171 $ — Depreciation and amortization $ 35 $ — Reclamation accretion $ 1 $ — Gold production costs (per oz sold): Direct mining and production costs $ 1,211 $ — By-product credits (1) — Royalties and production taxes 51 — Inventory change, write-downs, and other (325) — Costs applicable to sales (per oz sold) (2) $ 936 $ — Depreciation and amortization $ 193 $ — Reclamation accretion $ 6 $ — All-in sustaining costs (per oz sold) $ 1,256 $ — (1) Site acquired through the Newcrest transaction; results have been included from the date of acquisition on November 6, 2023. (2) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 28 -- 28 of 30 -- AHAFO Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 1,375 665 Open pit waste 5,273 6,302 Total open pit 6,648 6,967 Total underground ore (000 tonnes): 636 587 Tons milled/processed (000 tonnes): Mill 2,510 2,505 Average ore grade (g/tonne): Mill 2.573 1.742 Average mill recovery rate 93.8 % 92.5 % Gold produced (koz): Consolidated/Attributable 190 128 Gold sold (koz): Consolidated/Attributable 184 131 Gold production costs ($M): Costs applicable to sales (1) $ 159 $ 130 Depreciation and amortization $ 51 $ 39 Reclamation accretion $ 2 $ 2 Gold production costs (per oz sold): Direct mining and production costs $ 678 $ 920 By-product credits (2) (2) Royalties and production taxes 154 120 Inventory change, write-downs, and other 35 (46) Costs applicable to sales (per oz sold) (1) $ 865 $ 992 Depreciation and amortization $ 278 $ 301 Reclamation accretion $ 10 $ 13 All-in sustaining costs (per oz sold) $ 1,010 $ 1,366 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 29 -- 29 of 30 -- AKYEM Three Months Ended March 31, 2024 2023 Open pit tons mined (000 tonnes): Open pit ore 494 988 Open pit waste 4,284 6,942 Total open pit 4,778 7,930 Tons milled/processed (000 tonnes): Mill 1,874 1,883 Average ore grade milled (g/tonne): Mill 1.285 1.288 Average mill recovery rate 87.9 % 88.7 % Gold produced (koz): Consolidated/Attributable 69 71 Gold sold (koz): Consolidated/Attributable 75 78 Gold production costs ($M): Costs applicable to sales (1) $ 76 $ 63 Depreciation and amortization $ 30 $ 29 Reclamation accretion $ 3 $ 3 Gold production costs (per oz sold): Direct mining and production costs $ 774 $ 822 By-product credits (6) (9) Royalties and production taxes 128 99 Inventory change, write-downs, and other 110 (102) Costs applicable to sales (per oz sold) (1) $ 1,006 $ 810 Depreciation and amortization $ 396 $ 370 Reclamation accretion $ 46 $ 38 All-in sustaining costs (per oz sold) $ 1,254 $ 1,067 (1) Excludes Depreciation and amortization and Reclamation and remediation. NEWMONT FIRST QUARTER 2024 | OPERATING STATISTICS 30 -- 30 of 30 --