TRANSCRIPT

Q1 2023 — Transcript

Q1 2023PDF · 23 pages247 KB
Alcoa Corporation
First Quarter 2023 Earnings Presentation and
Conference Call
Wednesday, April 19, 2023, 5:00 PM Eastern
CORPORATE PARTICIPANTS
Roy Harvey – President and Chief Executive Officer
Molly Beerman – Executive Vice President and Chief Financial Officer
James Dwyer – Vice President, Investor Relations and Pension Investments
OTHER PARTICIPANTS
Michael Dudas – Analyst, Vertical Research Partners LLC
Lucas Pipes – Analyst, B. Riley Securities, Inc.
Timna Tanners – Analyst, Wolfe Research LLC
John Tumazos – Analyst, John Tumazos Very Independent Research LLC
Carlos de Alba – Analyst, Morgan Stanley & Co. LLC
Emily Chieng – Analyst, Goldman Sachs & Co. LLC
Alexander Hacking – Analyst, Citi Investment Research
Lawson Winder – Analyst, BofA Securities

-- 1 of 23 --

1
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
PRESENTATION
Operator Good afternoon, and welcome to the Alcoa Corporation First Quarter 2023
Earnings Presentation and Conference Call. All participants will be in a
listen-only mode.
Should you need assistance, please signal a conference specialist by
pressing the star key followed by zero. After today’s presentation, there will
be an opportunity to ask questions. To ask a question, you may press star
then one on your phone. To withdraw your question, please press star then
two. Please note, this event is being recorded.
I would now like to turn the conference over to James Dwyer, Vice
President of Investor Relations. Please go ahead.
James Dwyer Thank you, and good day everyone. I’m joined today by Roy Harvey,
Alcoa Corporation President and Chief Executive Officer, and Molly
Beerman, Executive Vice President and Chief Financial Officer. We will
take your questions after comments by Roy and Molly.
As a reminder, today’s discussion will contain forward looking statements
relating to future events and expectations that are subject to various
assumptions and caveats. Factors that may cause the Company's actual
results to differ materially from these statements are included in today’s
presentation and in our SEC filings.
In addition, we have included some non-GAAP financial measures in this
presentation. Reconciliations to the most directly comparable GAAP
financial measures can be found in the appendix to today’s presentation.
Any reference in our discussion today to EBITDA means Adjusted EBITDA.
Finally, as previously announced, the earnings release and slide
presentation are available on our website.
With that, here’s Roy.
Roy Harvey Thanks, Jim. And thank you to everyone for joining our call.
We are joined today by our new Executive Vice President and Chief
Financial Officer, Molly Beerman. As you recall, she was appointed as CFO
in February of this year, and though this is her first formal presentation of
our quarterly financial results, she’s no stranger to the process – she had
been Alcoa’s principal accounting officer and controller since 2016, and I’m
pleased to have her as a member of my executive leadership team.
Also, our former CFO, Bill Oplinger, is now Executive Vice President and
Chief Operations Officer, where he is working with our production leaders
to reinforce a safe and stable operating environment, and to drive
continued improvement across all of our assets. Together, my executive
leadership team is working with Alcoans around the globe to help advance
our company’s purpose and vision, as outlined on the left of this slide.

-- 2 of 23 --

2
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
At Alcoa, we all work together to turn raw potential into real progress. The
progress we make as a Company matters – it matters for our investors,
customers, employees, and communities. And it matters for society, as the
world will need more responsibly produced aluminum in the future. We
constantly remind ourselves of the importance of our actions – whether in
operations, in our offices or as we make corporate decisions.
And faced with a volatile market environment, as well as continued
challenges at some of our operations, we continue to focus on three
strategic priorities:
First, we work to reduce complexity, which means operating with a lean,
cost-focused approach and actively managing our portfolio of assets to
drive profitability through all phases of the commodity cycle.
Second, we strive to drive returns through margin-focused growth via
purposefully allocated capital and differentiated, value add products. That
means consistently working to improve our commerical capabilities through
quality, technical excellence, and delivery performance.
And our third priority is to advance sustainably, which means more than
just championing environmental, social and governance processes. We
also work to create value and maintain a strong balance sheet while
developing breakthrough technologies that have the potential to
decarbonize the aluminum value chain.
In the first quarter, we saw sequential improvement across our key
earnings metrics. Notably, we increased our Adjusted EBITDA from the
fourth quarter by more than $211 million, posting a result of $240 million.
Molly will dive deeper into our financial results shortly. But first, I’d like to
reiterate, once again, our continuing commitment to Alcoa’s values and
particularly to safety.
No matter where we operate, we strive to ensure that our employees,
contractors and visitors remain safe at our locations. In the first quarter, we
did not have any fatal or serious injuries. However, we continue to have
near misses, or potential incidents, which we closely monitor and use as
opportunities to accelerate our learning. So we must -- and we will --
continue to work on identifying and eliminating operational risks that could
result in injuries to our employees. We hold ourselves accountable to
continuously improve the safety of our work environments, and to ensure
that everyone arrives home safely.
Next, as you see on this slide, in the first quarter, we made adjustments to
operating levels at some of our locations. We’ll discuss more about that
later in this call, including the agreement we successfully negotiated in
Spain on the restart of our San Ciprian smelter and progressing the full
restart of the Alumar smelter in Brazil.
Finally, our commercial team recently introduced an expansion of our
SustanaTM family of low-carbon products. Our EcoSourceTM low-carbon
alumina brand now includes non-metallurgical grades. This complements

-- 3 of 23 --

3
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
our existing smelter-grade product, also marketed under the EcoSource
brand.
So, with those introductory remarks, let’s go to the financials. Molly, please
go ahead.
Molly Beerman Thank you, Roy.
We saw broad improvement from the fourth quarter of 2022 to the first
quarter of 2023. Realized prices were higher for both aluminum and
alumina, with aluminum up seven percent and alumina up eight percent
sequentially, while revenues remained flat at $2.7 billion on lower
shipments.
Stable revenues and lower costs were reflected in an improved bottom line.
The net loss per share attributable to Alcoa improved by $0.94, to $1.30,
and the adjusted loss per share improved $0.59, moving from $0.82 to
$0.23.
Adjusted EBITDA excluding special items also improved considerably:
increasing from $29 million to $240 million.
Let’s look more closely at the key drivers of adjusted EBITDA.
The $211 million increase in adjusted EBITDA was propelled by
improvements across most of the bridge. While we saw unfavorable
currency impacts due to a weaker dollar, higher metal and alumina prices
provided $148 million, or 70 percent, of the sequential quarterly
improvement. The remainder came from several items: lower energy costs
in the first quarter 2023 and the absence of the CO2 costs realized in the
fourth quarter 2022, primarily in Norway, price/mix was favorable due to
improved value add pricing in Europe, especially rod, as well as higher third
party bauxite prices, and the other category was favorable due to the non-
recurrence of the Alumar ARO adjustment made last quarter and lower
spending outside the segments, especially in Transformation.
Other than foreign currency, the only unfavorable performance was higher
production costs, due to two locations: the Alumar refinery and the
Portland smelter.
This is the first quarter the Bauxite and Alumina segments have been
combined into the Alumina segment. To help with comparisons, we have
provided the previously reported 2022 quarterly segment adjusted EBITDA
recast into the new Alumina segment within the appendix.
Looking from fourth quarter 2022 to first quarter 2023 on a comparable
basis, the Alumina segment adjusted EBITDA more than doubled on
stronger API pricing and product mix, partially offset by higher costs, both
production and raw materials. Currency was unfavorable in both
segments. For the Aluminum segment, outside the currency impact, higher
metal prices, lower alumina costs and lower energy costs hit the bottom
line, while stronger value add product pricing combined with lower raw
materials costs completely offset other unfavorable costs.

-- 4 of 23 --

4
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Now let’s turn to other financial metrics and cash flow.
While sequentially higher Adjusted EBITDA increased cash flow potential,
our typical first quarter working capital build offset those gains. $216 million
of increased working capital was the largest use of funds in the quarter and
a key driver of negative $166 million free cash flow less net NCI
distributions.
We expect the 56 days of working capital to reduce as the year progresses.
Cash ended the period at $1.1 billion and proportional adjusted net debt
rose to $1.4 billion. We again paid our $0.10 per share dividend in the first
quarter, totaling $18 million.
For a little more granularity on working capital and cash flow, let’s look at
raw materials and inventories.
Given the significance of raw materials in the value of our inventory, they
are a key driver of both profitability and cash flows. Three materials are
dominant in our business: caustic for our Alumina segment, and petroleum
coke and coal tar pitch for our Aluminum segment.
Looking at market index prices for the past year, all three commodities are
coming off their peaks. We are seeing considerable recent improvement
in caustic prices, as well as more gradual improvements in quoted prices
for coke and pitch. These price improvements flow into our inventory
valuation and, as we have previously shared, it can take one or two
quarters before the purchase price improvement starts to flow through
COGS and hit the income and cash flow statements. That said, should
these raw material price trends continue, we expect to be rewarded with
lower inventory valuations, lower COGS related to raw materials, and
improved cash flow. Now let’s turn to our expectations for the year and
provide comments on the second quarter.
At this point, we are not making updates to our full year outlook, for either
the income statement or cash flow items.
Regarding sequential changes for the second quarter:
In the Alumina segment, we expect an approximately $55 million
unfavorable impact from lower bauxite grades in Australia. In addition, we
expect a net unfavorable impact of $10 million as higher seasonal
maintenance, volume changes and impacts associated with the Alumar
conveyor system recovery are partially offset by improvements in raw
materials and energy.
In the Aluminum segment, we expect a net improvement of $30 million as
favorable raw materials, volume and lower production costs are only
partially offset by changes in value add premiums. In addition, we expect
$5 to $10 million in unfavorable impacts associated with the Portland partial
curtailment. Finally, we expect alumina costs in the Aluminum segment to
be unfavorable by $15 million.
Below the EBITDA line:

-- 5 of 23 --

5
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Other expense is expected to be approximately $30 million favorable,
primarily due to the absence of a one-time charge taken in the first quarter.
Based on recent pricing, the Company expects second quarter 2023
operational tax expense to approximate $30 to $40 million.
Now, I will turn it back to Roy.
Roy Harvey Thanks, Molly.
I’d like to start with what we’re seeing in the global alumina and aluminum
markets. Then, I’ll highlight some potential implications and a few
commercial developments specific to Alcoa.
At a macro level, the global alumina and aluminum markets both remain in
balance. In China, however, there are slight deficits for both products.
Meanwhile, the regional markets in the rest of the world are in a slight
surplus for both alumina and aluminum.
For the long term, we continue to believe that aluminum demand will rise
significantly, driven by global decarbonization strategies. The International
Aluminium Institute, for example, is forecasting global aluminum demand
to increase up to 80 percent by 2050 from a baseline of 2018 and that will
require both new primary and secondary capacity.
This year, global inventories of aluminum are expected to be at historic
lows. With such low inventories, if demand normalizes in China or the rest
of the world, those supplies will be insufficient.
Now, moving to the right-hand side of this slide, you’ll see some recent
aluminum supply changes in the first quarter of this year. On the supply
side, we saw more curtailments than restarts. While power costs have
eased in some places outside of China, it was not enough to support
significant restarts.
Meanwhile, in China, the supply situation could potentially move the world
market into a deficit. There have already been curtailments of
approximately 1 million metric tonnes in two key regions. And the restart of
curtailed capacity in Yunnan is heavily dependent on hydroelectricity,
which is seeing supply shortages. The smelters operating in that province
are producing below capacity, and analysts have noted that they may be
asked to further reduce output and/or switch to coal-generated power.
In key end markets for aluminum, we see automotive production continuing
to strengthen, which is supportive of the demand for flat rolled products.
The market for construction products remains challenging given high
interest rates. Foundry, slab and rod markets remain strong, while billet
demand is soft in Europe and North America.
Next, regarding the production and warehousing of Russian metal: in
February, the U.S. Government placed a 200 percent tariff on Russian
metal imports.

-- 6 of 23 --

6
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
The U.S. has taken a strong first move with these tariffs that were
implemented as a punitive measure for the country’s invasion of Ukraine.
The government is also tracing Russian origin metal in various imported
products. However, we believe there is more that can be done.
While many Rest of World smelters remain curtailed, Russian smelters
continue to produce at full capacity. Thus, we continue to advocate with our
governments for full sanctions on Russian origin aluminum.
As many aluminum customers self-sanction against Russian metal,
unwanted Russian tonnes are being stockpiled in London Metal Exchange
warehouses and are threatening to undermine the reliability of the LME as
a global pricing reference for aluminum.
As you may recall, Alcoa warned that the LME aluminum contract was at
risk of becoming dislocated from the physical market, as LME warehouses
would eventually receive a disproportionate amount of unwanted Russian
stocks.
The data should prompt concern. As of the end of March, Russian stocks
in LME warehouses increased to 53 percent of the total inventories. That
compares to approximately five percent of the total prior to the invasion of
Ukraine. We expect that further stockpiling of Russian material will occur
throughout the year and into the future. If this trend continues, the LME’s
aluminum price reference will be relegated to a price for unwanted,
warehoused Russian aluminum, which much of the world refuses to
purchase or consume.
Given these developments, we continue to advocate with our host
governments to apply full sanctions on Russian origin aluminum, and we
are strongly urging the LME that Russian metal be delisted as a deliverable
brand.
Now let’s turn to our own commercial developments: We have already seen
some increased volumes and new contracts as customers continue to look
for alternatives to Russian-supplied material. Within Europe, several large
customers require guarantees that no Russian aluminum exists within their
suppliers’ materials, as it could result in substantial tariffs should their
products be exported to the United States.
Finally, I want to highlight the news about our Sustana family of low-carbon
products, comprised of EcoSource alumina, EcoLumTM aluminum and
EcoDura aluminum with recycled content.
Last year, we saw nearly a five-fold increase in sales volumes for EcoLum,
which is manufactured with an emissions intensity that is three times better
than the industry average. We offer it in a range of products, including billet,
foundry, slab, wire rod, unalloyed high purity, and commodity-grade P1020.
While these annual volumes are still a small portion of our overall sales
volume, we’re building on last year’s good growth with an expected
additional 30 percent in increased sales this year, particularly in Europe.

-- 7 of 23 --

7
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
We expect this trend to continue with more customers committing to
aggressive decarbonization targets.
And as I mentioned at the top of our call, we also expanded our EcoSource
product line to now include non-metallurgical alumina (or NMA), as well as
the smelter-grade product we launched in 2020. These EcoSource
products are unique across our industry, and are unmatched by our
competitors.
The expansion of our EcoSource brand helps leverage our advantages as
a producer of SGA and NMA with a low carbon dioxide intensity. Our
EcoSource product has its greenhouse gas calculations verified by a third-
party. And we can deliver from a global refinery portfolio that has an
average emissions intensity that is half the industry average.
Now, I’d like to turn our attention to our operations. We made several
reductions of capacity in the quarter as we ramped up production in others.
Our Canadian facilities include three smelters that we operate in Quebec:
Deschambault, Becancour and Baie-Comeau. All are powered by
hydroelectricity, and together they are currently operating at near peak
levels.
In the United States, we have improved operational stability at our Warrick
smelter for the two operating potlines. Also, in the United States, we made
the strategic decision in March to permanently close the Intalco smelter
after evaluating various options for the asset, including a potential sale. It
had been fully idle since 2020, and the land at that site has now transferred
to a new owner who is working on economic development opportunities.
Our Transformation group, which manages curtailed and closed sites, has
done a good job to position this site for new productive uses.
In Brazil, we are continuing with the restart of the Alumar smelter, which is
now producing at approximately 60 percent of capacity, and continues to
accelerate production.
Alumar also includes a co-located alumina refinery. On March 25, a ship-
to-shore conveyance system collapsed, temporarily halting the flow of
bauxite to the refinery. While investigating this failure to root cause, our
teams safely executed critical repairs to restore the flow, thus enabling the
refinery to continue to operate. These repairs were important and time-
sensitive activities, and the teams did a great job completing them safely
and swiftly.
Now that bauxite is being delivered to the refinery, we are building back the
on-site inventory and gradually ramping up production. Our expectation is
to reach full production levels by the end of this month. We continue to
make all customer shipments of alumina from the refinery through this
period.
Now, moving to Europe, and our San Ciprián complex, which includes our
refinery and the fully curtailed smelter. At the refinery, we reduced the
production rate last year to help mitigate the high costs of natural gas in

-- 8 of 23 --

8
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Spain. We are now operating at approximately 50 percent of the refinery’s
1.6 million tonnes of annual capacity, and continue to analyze the most
advantageous run rate given market conditions.
For the San Ciprián smelter, in February, we successfully reached an
agreement with the workers’ representatives to commence the restart
process in phases beginning in January 2024. We currently have two long-
term wind-sourced power purchase agreements that can support a portion
of the smelter’s needs, pending permitting, development, and construction
of the wind farms. As part of our agreement with the workforce, we are also
moving forward with capital projects that will help support this restart and
the future competitiveness of this facility.
In Norway: We continue to operate two of the three potlines at the Lista
smelter – you will recall one line was curtailed last year due to exorbitant
spot energy prices. We have now fixed our energy costs for Lista’s two
potlines through 2023, which provides short-term stability during highly
volatile energy markets. Meanwhile, our other Norwegian smelter,
Mosjoen, is operating stably and near full pot complement, as is our
Fjardaal facility in Iceland.
Finally on this slide, let’s discuss Australia: In March, the Portland
Aluminium joint venture reduced its production to approximately 75 percent
of its total annual capacity; Alcoa’s share of the capacity is 197,000 metric
tonnes per year. We have restored stability at this site, which had
experienced challenges related to the production of rodded anodes.
At our Kwinana refinery, we made the decision to keep one of five digesters
curtailed. It was first curtailed due to a state-wide shortage of natural gas.
Given an extended process for our mine approvals in Western Australia,
we have decided to keep this digester curtailed.
Delays in our bauxite mine approvals process in Western Australia has also
prompted us to extend mining in previously approved areas by extracting
lower grade bauxite beginning in the second quarter of this year, as we
commented during last quarter’s earnings presentation.
Next, I’d like to talk a little more about our approach to responsible mining
globally, and particularly about our bauxite mining operations in Western
Australia, a region where we have operated for 60 years.
First, I want to stress that we appreciate and understand the increasing
expectations that stakeholders have for mining operations. Sustainability
has been core to our focus at Alcoa, and it’s one overriding priority that
helps differentiate our Company. In fact, it’s why we have the strategic
priority to advance sustainably.
We believe that delivering on our stakeholders’ expectations is a key to our
success moving forward. We strive to maintain our commitment to safe and
responsible operations, including proactive engagement with our
communities before, during, and after bauxite mining. We also know the

-- 9 of 23 --

9
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
world is evolving, and we are committed to continually improving our
practices and meeting modernized expectations.
As we work to address evolving challenges facing the mining industry, we
cannot lose sight of how important aluminium is now and will be in the
future. It’s a fact that aluminum is critical to a more sustainable future
because it’s used in electric vehicles, renewable energy, and numerous
other aluminium-intensive products that can help the world meet ambitious
decarbonization goals.
Producing the aluminum that the world needs now, and for the future, will
require bauxite mining. But mining must be done the right way.
We intend to mine in a responsible way that protects the environment and
creates value for our host communities. And we are focused on delivering
on those expectations and implementing improvements whenever they are
needed.
Currently, we have two significant areas of attention for our Western
Australian mines – Huntly and Willowdale: The first is the protection of
public drinking water and the second is the restoration of the forest and its
biodiversity.
In our long history of operations, we have never negatively impaired the
supply of drinking water in Western Australia, and we do not intend to
compromise that record. That’s why we are currently working through a
detailed environmental, technical, and economic assessment on additional
protection measures that can be included in our mining plans.
We also are committed to protecting the biodiversity of the northern jarrah
forest. We have long taken pride in our rehabilitation efforts. Among our
many successes was to be the first mining company in Australia to officially
hand back a significant area of rehabilitated land, and we are one of the
few mining companies in Western Australia to have ever done this.
Today, about 75 percent of all areas we have cleared for mining have been
rehabilitated and are at different growth stages – from early plantings to
developed forest. But again, we intend to continue to evolve and improve,
including accelerating rehabilitation in open areas.
Protecting water supplies and restoration are focal points as we
cooperatively work with government regulators on modernizing our
approvals framework for our Huntly and Willowdale mines. We are also
considering how we can reduce potential social impacts through this
process.
Now, let me spend a few minutes explaining our current situation with mine
permitting. The Huntly and Willowdale mines are currently subject to a
bespoke approvals process that is conducted annually on a five-year rolling
basis. As we said last quarter, this process is taking longer than in prior
iterations due to increased expectations towards a modernized approvals
framework.

-- 10 of 23 --

10
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
In response to these delays, we are extending mining in areas already
permitted under existing approvals; that means mining bauxite with a lower
quality or grade, using more caustic, and producing less alumina.
Also, during the first quarter of this year, a third party referred our current
and future mine plans for Huntly and Willowdale to the Western Australian
Environmental Protection Authority for assessment.
The third-party referral will likely result in further delays, with bauxite grade
impacts expected to continue until at least the first quarter of 2024.
Remember that it requires considerable planning and development to
reach new bauxite areas, which we have included in this projection of future
bauxite grades.
It’s important to note here that prior to these referrals, we had proactively
initiated our own EPA assessment process for the extension of our
operations to the future Myara North and Holyoake regions of the Huntly
Mine. This process is commonly known in the State of Western Australia
as an EPA Part 4 assessment. As we transition to this process for future
regions, we believe the current statutory process for Huntly and Willowdale
can be adapted to provide enhanced environmental protections and be
successfully applied to our current mining operations.
As noted, we continue to work with relevant government bodies to support
these annual approvals processes. We are also responding to requests for
information from the state EPA to support the authority’s consideration of
whether the third-party referrals are valid and require assessment.
This is a complex and evolving situation, and we are fully committed to
reaching a collaborative agreement with the Western Australia government
to protect the environment, meet stakeholder expectations, and maintain
the vital economic benefits that our operations provide.
In closing, I want to quickly summarize three key elements from our
presentation today.
First, we saw improvement in our key earnings metrics during the first
quarter – we grew our EBITDA to $240 million. And we also maintained a
strong balance sheet with $1.1 billion in cash and low proportional adjusted
net debt.
We continue to drive for improvement in our financials, and our operations.
While we have challenges that we need to solve, we are laser focused on
operational stability and consistent improvement. And we are seeing
progress.
From a leadership perspective, we help set the priorities and the direction,
but our teams on the ground turn it into reality. They make it work by what
they do every minute, every shift and every day. I’m proud of the more than
13,000 employees we have across the globe – and their commitment to
continuously improve. I look forward to continuing to report on these
improvements as the year progresses.

-- 11 of 23 --

11
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Finally, the long-term fundamentals of our industry remain strong; demand
for our metal is expected to grow in the future as customers seek lower-
carbon raw materials across the supply chain. Aluminum is lightweight,
strong, highly conductive, and recyclable, making it ideally suited for a wide
range of applications, including electric vehicles and renewable energy
infrastructure.
We are working to deliver more sustainable solutions through technologies
we have under development to decarbonize aluminum production and
advance recycling technologies, in support of our vision to reinvent the
aluminum industry for a sustainable future.
And, with that, Molly and I are ready to accept your questions. Operator,
who do we have on the line for our first question today?
QUESTION AND ANSWER SECTION
Operator Thank you. We will now begin the question-and-answer session. To ask a
question, you may press star then one on your phone. If you are using a
speaker phone, please pick up your handset before pressing the keys. To
withdraw your question, please press star, then two. When called upon,
please limit yourself to two questions. We will pause momentarily to
assemble our roster. And our first question comes from Michael Dudas with
Vertical Research. Please go ahead.
Michael Dudas Good morning, gentlemen and Molly.
Roy Harvey Hey, Mike.
Jim Dwyer Hey, Mike.
Michael Dudas First question is, your observations on rest of world capacity and the lack
of restarts even though energy, power prices have corrected downward
somewhat. Is the demand outlook and the energy outlook an uncertainty
given geopolitics? Even if prices stay low, does it still make it more difficult
for capacity restarts in the market, in your view?
Roy Harvey Yeah. Michael, let me handle that one. So, first and foremost, what I'd say
is that we have seen pricing come down and particularly in Europe. So, it
is significantly better but still significantly higher priced than it was prior to
the invasion of Ukraine. And so, we're seeing relief, but it still isn't, in my
perspective, enough relief really to drive a fundamental shift in the ability to
smelt aluminum in Europe.
The second side of it on the demand side, realistically speaking, I think the
demand is still there. And particularly as you look at a number of companies
essentially putting in their own set of sanctions against Russian metal, it
means that we've got more interest in our volumes coming out of Europe.
And so, there's demand available; it's just that the margins are pretty tight.
So, when you take the fact that across the aluminum industry, margins are
tight because costs are still high, they are coming down. So, when we look
out these next quarters, we're going to continue to see raw materials relief.
Margins are still thin. So, when energy prices are high and the average

-- 12 of 23 --

12
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
margins are thin from around the world, it's just not justifying or incentivizing
significant restarts.
Michael Dudas That’s a solid observation. And my follow-up would be, and given your
remarks relative to China of having deficits or slight deficits in alumina and
aluminum, can you speak about some of the dynamics in the alumina
market or actually in both markets where is there a propensity for one to be
a little bit more closer to balance or oversupplied or vice versa, given some
of the power challenges or some of the demand challenges you're seeing
on the primary side?
Roy Harvey Yeah, Michael. I think it's a really good question. And I think the answer's
got to be that both markets are thinly balanced and could move in either
direction, right? You look at aluminum, for example, in China, really good
strong demand increase. But on the supply side, there's just not enough
power in the southwestern provinces. And so, we're seeing the likelihood
for more further curtailments, which means it drives them into an even
bigger deficit which then then ends up with the deficit in the whole world,
as an example.
On the alumina side, it's not necessarily a different perspective, right? In
Europe with natural gas prices again, they're better than they were, but
they're still significantly increased from where they were, natural gas and
all the different other sources of energy that are available. So, it means that
refining in Europe, and we see this in our San Ciprián refinery, it's why
we're running at 50 percent, is really difficult and is either extremely thinly
margined or more likely a loss maker. So, my point is both markets really
are finely balanced. And so, when we look at the short term, it's just hard
to call which way they're going to go.
Now, somehow that's going to bridge to a longer term. And I am convinced
and enthusiastic about the long term because we're seeing real
expectations on where new demand sources are going to come in, when
you look at electric vehicles, when you look at the renewable energy and
the need for aluminum as part of the infrastructure. And there just isn't
enough new capacity coming online in order to be able to answer that
aluminum demand or realistically to be able to answer that alumina demand
either. And so, all that comes together to say we're in a balanced and finally
sort of very finely balanced market today. But at some point, that is going
to get to this medium to long term where we have a much more positive
future.
Michael Dudas Roy, appreciate your thoughts. Thank you.
Roy Harvey Thanks, Mike.
Operator The next question comes from Lucas Pipes with B Riley Securities. Please
go ahead.
Lucas Pipes Thank you very much, operator. Good afternoon, everyone. Roy, I also
have a higher level question to kick things off, and there are a lot of
commentators out there calling for eight, nine, 12, even 20-plus dollar

-- 13 of 23 --

13
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
copper prices per pound. And in that sort of world, where in the market and
in what sort of applications would you see aluminum substitution? And is
there enough discipline? I think you just kind of answered that question in
the aluminum industry today, that this would also pull up aluminum prices.
Would really appreciate your perspective on that. Thank you.
Roy Harvey Yeah, Lucas, I can give you an answer. I'm not sure if it will cover all the
bases but at least it gets you started. We look at history and it tells us that
there is a real arbitrage that people play when it comes to copper and
aluminum. And in fact, the two prices tend to be pretty closely connected
through time, although you do see some variations in that. As copper prices
start to jack up, I think we're also seeing some positives in the aluminum
price as well. I was happily watching it over the course of today, and that
certainly makes a big difference to us. I think they'll tend to be connected.
But the more the copper price runs, the more substitution you're going to
see back into aluminum. Because the fact is that aluminum tends to be very
versatile. It is infinitely recyclable and it's available, right? The fact is that
we have available inventories and we have the ability to ramp up
production.
At the same time, I think your other point is really quite key to understanding
the future. There's just not a lot of new production that's going to come
online. You've got some smelters that can restart. You've got the potential
for some growth happening in Southeast Asia and in the Middle East, for
example. But outside of that, there's just not a lot of projects. And so, as
that demand grows, as some of that substitution happens, there's just not
a clear place where that new demand is going to come in. Part of the
solution will be recycling.
And I think that's an area we've got a breakthrough technology that we're
working on with recycling to be able to better manage post-consumer
scrap. So, that is going to be supportive. But there's also just not enough
metal. You're going to need primary metal and it's going to have to come
from somewhere. And so that's all stuff that needs to be designed and
figured out on how we're going to be able to address that. But that's what
leads me to my very positive view on the medium to long term in our
industry.
Lucas Pipes Roy, I really appreciate that, the color. And as a second question, switching
topics, I appreciated the update on and reminder on the San Ciprián restart
plans on the smelter side. Is there kind of a minimum utilization that we
should think of for 2024? Thank you very much for your color on that.
Roy Harvey Yeah. What we've tried to do is match the progress of the restart with the
new contracts that we've signed, the new energy capacity coming online.
And because it takes time to actually permit and then construct those new
wind farms, it means a lot of that capacity is going to be pointed more
towards 2025 rather than 2024. So, we have a commitment to get started
in 2024 by January 1st. It's, if I remember right, five percent of the total
output. So, it's a relatively small piece of it that gets us started. If we get
new wind capacity coming in, we can start to ramp that up, because it's

-- 14 of 23 --

14
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
very low priced energy and we'd be glad to be smelting aluminum at those
levels. But really, we need to be up and fully operational by October of
2025. That's a firm commitment that we have on our end. I think it matches
what we've been able to build on the energy side. And to be quite honest,
we're putting a lot of effort into making the San Ciprián smelter a
competitive smelter for the long-term.
Lucas Pipes That is very helpful. Really appreciate your color, and to you and the team,
best of luck.
Roy Harvey Thanks, Lucas.
Operator The next question comes from Timna Tanners with Wolfe Research.
Please go ahead.
Timna Tanners Yeah. Hey, good afternoon, guys. I wanted to kick off, if I could, talking
about the unchanged guidance on shipments for aluminum and alumina.
We just thought it was a little surprising given some of the disruption. So, I
just want to make sure I understood. It seems like perhaps that Alumar was
brief and doesn't matter. Maybe the other refineries, small impacts, but I
just want to make sure I understood fully that maybe they were smaller or
maybe you are expecting some improvement as the year progresses to
keep volumes the same.
Molly Beerman Hi, Timna. I’ll take this one. So, in regard to the alumina guidance, we had
a good outlook on the WA bauxite situation so that was built into the
guidance for the year. The Alumar refinery, the interruption is slight, we do
expect to catch up and be on target for the year. And in aluminum, we're
still tracking well to the guidance.
Timna Tanners Okay, great. I have so many more questions.
Molly Beerman And I should have added that we haven't made decisions yet on the
Portland restart. So, again, not a huge volume there with 25 percent down,
but that's one provision on the aluminum.
Timna Tanners Got you. And that's somewhat small, so I can see how that might not move
the needle. Okay. I guess, I wanted to ask, if I could sneak in, on the bauxite
situation, I just want to clarify, you're expecting the extended unfavorable
mining circumstances to continue through the first quarter, but what's
embedded in your assumptions? Is it that you'll expect to be able to move
to your expected mine plan beyond that and what's baked in there? And
then if I could sneak in another one, on the energy exposure side, getting
a lot of questions about benefits to lower prices, but I believe you're pretty
well secured for the year. So, just sneaking that one in as well, if you could
comment on how much exposure you might have through the end of the
year to power prices? Thanks.
Roy Harvey Let me answer Western Australia and then I'll let Molly answer the energy
question. I think the key here on Western Australia is that we're still in the
midst of discussions with the Western Australian Government. And so,
we're not yet at an endpoint, as I’ve said in my comments, I'm confident

-- 15 of 23 --

15
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
that we are working collaboratively to reach that solution. What we built into
that assumption around going into first quarter of 2024 is that it typically
takes nine to 12 months to develop the plans and then to deploy on the
plans to essentially be able to change to new mining areas.
And so, that sort of helps you build your understanding of when we think
we're going to be moving our way through that permitting process and then
how long it takes us to be able to adapt and have the surety of where we're
going to be mining and when we're going to be mining. It takes about one
quarter to do the detailed planning to move from one grade to the next. So,
the quicker that we can finalize the discussions that we're having with
Western Australian Government, the quicker we can be very clear about
the extra measures that we need to take and what bauxite areas that we
will be moving to next and that like I said, it's an ongoing discussion with
the government.
The quicker we can get that done, the quicker we'll have surety of where
we’ll be, the amount of ore that we'll have available, and how much effort
and infrastructure it takes to be able to reach that ore, and then we can
start counting backwards on when we can do that, one quarter away from
changing the bauxite grades. So, I realize that's a lot of calculations that sit
inside of that. But as we look at it today, we think 1Q 2024 is our best
estimate for when we can see that the last of those impacts, but we'll keep
you updated as we progress. And Molly, I'll turn it over to you for energy.
Molly Beerman Timna, on your energy exposure question, you're right, we do have
everything secured now except one small piece in Norway. I do want to call
out the Lista smelter in Norway, we had highlighted a couple of quarters
ago, back in that third quarter of 2022 that site actually lost $45 million for
the quarter. And we're pleased to say that that is now running at near
breakeven and with further premium improvements, we could get some
more profitability out of that site. So, great turnaround for Lista where we've
secured the power through the end of the year.
Timna Tanners Okay, thanks for the details.
Roy Harvey Thanks, Timna.
Operator The next question comes from John Tumazos with Tumazos Very
Independent Research. Please go ahead.
John Tumazos Thank you. I'm trying to put together the different bits and pieces. Should
we expect something like a $10 a tonne cost increase in the Alumina
segment in the June quarter and something like a $0.03 or $0.05 fall in the
aluminum metal segment, which will, I guess, benefit more from pitch and
tar and energy?
Molly Beerman John, we didn't work it out to the tonne level, we can certainly do that. I
don't have that handy for you right now.
John Tumazos Thank you.
Roy Harvey Thanks, John.

-- 16 of 23 --

16
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Operator The next question comes from Carlos de Alba with Morgan Stanley. Please
go ahead.
Carlos de Alba Yeah. Thank you very much. Good afternoon, Roy and Molly. So, first
question is, coming back to the bauxite situation in Western Australia. So,
the guidance is for a sequential guidance for $55 million unfavorable impact
on lower grade bauxite in the country. Given that the situation extends until
the first quarter of 2024, how should we look at costs going forward? Is this
$55 million basically taking us to the level where you were going to be
throughout the first quarter until the first quarter of 2024? Or they could be
potentially higher and negative impact on this situation in the Alumina
segment? That would be my first question.
And my second question is, if you could maybe comment and provide a
little bit more detail on the value-added premiums that you are getting. And
if there is any differentiation between Europe and the U.S. that are
important for us taking into account?
Molly Beerman Okay. Carlos, first on the $55 million guidance and that is applying to the
second quarter, we do see opportunities to work on cost to reduce that and
we'll give you updates going forward. But for right now, the $55 million is
applying for our future look and that includes about $10 million impact of
volume and about $45 million for caustic, bauxite, and energy usage is
unfavorable at this bauxite grade.
Roy Harvey And, Carlos, just to tie into Molly's comments there, too. I mean, as we look
forward to the next quarters, we're essentially running the Western
Australian refineries at lower grades than we have before. And so, there's
a certain amount of learning that we're going to be doing as we go. And so,
like Molly said, the expectation is that we can learn, and we can improve
upon the operating efficiencies every quarter, but we don't want to make
promises and guarantees on that until we can be certain that we can show
that. So, we hope to report some good news for you coming into this next
quarter as we look towards future quarters.
On value-added premiums, when we look at it year-on-year, we continue
to see strength. The fact is we came into what was a pretty crazy year with
the first half with nothing but blue skies and the second half, a bit more
cloudy. Coming into this year, we're continuing to see strength. We're
seeing more strength, honestly, in Europe. Part of that's the self-
sanctioning, part of it's also because the energy situation is a lot better than
was expected. So, coming into the year, I think we're seeing better strength
in the volumes and, in the end, the volumes that impact the premiums that
we negotiate on a quarterly basis.
In North America, I think there was a bunch of uncertainty because of the
banking situation. I know there were a lot of questions what that might do
to demand. We seem to be successfully past that, at least for now. We're
certainly seeing better premiums than we were last year, but we're also
seeing a little bit of weakness on the billet side particularly, that's really
coming in from building and construction, which just isn't moving as quickly
as what we've seen in some other times.

-- 17 of 23 --

17
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
So, it's sort of a mixed picture. I think we're seeing year-over-year
improvements. We're sort of seeing a continued amount of uncertainty
when we look out at the next quarter and hope that with some of the
improvements that we're seeing in demand in China, particularly some of
the resolution around what energy prices are going to look like, and some
of the more surety about how much natural gas Europe is going to have
going forward, I think that starts to build a little bit more resilience back into
the market, which then has its knock-on impacts in our value added
products.
Carlos de Alba Alright. Thanks, Roy. So, should we interpret by your comments on
construction that we still haven't seen any meaningful impact from the
infrastructure bill approved last year in the U.S.?
Roy Harvey Carlos, we've seen a bunch of announcements and expectations. That's
not transferred through into orders yet. But I would say it's probably still a
little bit early for that money to be dispersed and for people to start turning
the ideas and concepts into actual on-the-ground orders. Again, we've had
a lot of interaction with governments around the IRA and obviously, in ways
that we can be able to use that to help promote our breakthrough
technologies. Just in some of the meetings that I've had, there's a lot of –
there tends to be when you have a group, you've got a lot of people around
the table that are very enthusiastic about investing in the U.S. and building
up capacity. And so, I have to say, I'm very bullish, but it's probably still a
little early to see that translate into specific orders for us.
Carlos de Alba Alright. Thank you very much.
Roy Harvey Thanks, Carlos.
Operator The next question comes from Emily Chieng with Goldman Sachs. Please
go ahead.
Emily Chieng Hi Roy and Molly, thanks for taking the questions. My first is just around
the Alumar smelter. I had thought that this was going to be a nine-month
process in ramping the smelter back to full capacity. So, curious, what's
driving the delay there? Is it operational or is there some intentional
throttling of volumes back given the pricing environment?
Roy Harvey Yeah, Emily, I'll take that one. It's more, I guess, logistical and operational
in nature. Logistical from the fact that when we were first getting started
restarting Alumar – and I know the plant well, I used to work there – it was
just harder to get the quality of raw materials that we needed to have the
kind of restart that we had expected. So, that was a bit of a disadvantage
when we were getting started. I think we've been able to iron out those
issues so now we have the qualities that we need, to be honest, because
we have a good portion of the smelter already operating. It means that you
have the raw materials on hand, and you're able to generate some of the
bath and hot metal that you need in order to restart that next set of pots.
The other surprise we had in Alumar is that, as we got started with those
pots that a lot of them had been relined, but others had not been relined,

-- 18 of 23 --

18
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
as we started them, we just didn't get the ability to keep them operating for
as long as we had expected. And to say it another way, we had more
failures than we expected to have during the restart process. I think that
comes down to the fact that it was idle for a good portion of time, a number
of years.
So, we've now got that sort of back on the road. We’re, essentially, where
we expected to be on the restart the last time we reported at the end of Q4.
We have the right management and the right people working on this, and I
think we're making real steady progress. And I'm super enthusiastic about
that team and about that facility for the long term because of the great
power contract that we have and the strength of operations.
Emily Chieng Understood. That makes a lot of sense. And maybe shifting gears to San
Ciprián and I wanted to talk about the refinery there, I believe the gas
environment for San Ciprián or gas contracts or rather the price that it's
bought, at what point, given where gas prices are today, is there any
consideration to bring back some of the refining capacity there?
Roy Harvey So I'll take that one and Molly can jump in, if she has some quantitative
comments as well. We're essentially running at 50 percent capacity. And I
can promise you that running a refinery at 50 percent is never the ideal
point. And really what we've been targeting is to try and focus as much on
non-metallurgical grade alumina because those tend to be higher priced
contracts and for more specialized operations.
But we're also selling some smelter-grade alumina as well. We analyze
almost continuously to see at what point have natural gas prices come
down. And then when you look at the price of SGA in the market, does that
create a business case for restarting more of that capacity? I'll put in a short
advertisement. We have a great workforce in San Ciprián. They really run
that refinery really well. They're running it at levels they've not for a very
long time. And I'm very pleased with what they've done. And we're on top
of things to see when we can make that natural gas price connect with the
market environment so that we can bring that capacity back up online
again.
Molly Beerman I'll just add that we did see about a $20 million sequential improvement
there for that site this quarter. So great progress.
Emily Chieng Fantastic. Thank you.
Roy Harvey Thanks, Emily.
Operator The next question comes from Alex Hacking with Citi. Please go ahead.
Alex Hacking Yeah, thank you. I just have a quick follow-up on WA. When will the state
EPA make a decision about whether or not to accept the third-party
referral? And if they do decide to accept that referral, what is the practical
implication of that, sort of, what happens next? Does that constrain your
ability to operate in any way and develop new mine plans? Thank you very
much.

-- 19 of 23 --

19
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
Roy Harvey Yeah. Alex, I'll take that one. So, we're in the midst of sort of the data
collection phase where the EPA is considering really two things. Number
one is the referral valid, which means is it valid, does it fulfill all the
requirements for actually having a referral and then assuming that it's valid,
then going into deciding whether, in fact, it should be assessed, i.e., should
there be another process to determine what are the current and then
medium and long term environmental impacts of that specific project. So,
that process will take some time.
We don't have a specific estimate because that timeline is really reset every
time they have another data request. And so, it's going to take a little bit of
time. The reason that we essentially structured what we've said about our
bauxite grade impact and extending it really into the first quarter of 2024
should give you a pretty good feel for what we think that this is going to add
to the process, assuming it plays out the way that we should.
I can't really jump into hypothetical situations about what that process is
going to come out and what then does it mean. The fact is there's not a
clear standard for what happens next. I think I would go back to say the
state's EPA and the referrals process, as well as the current discussions
around the operating permits is really all managed at the Western
Australian level. So, the work that we're doing in order to try and solve all
of these problems is to make sure that we have the mitigations in place that
we're protecting the watersheds and ensuring that we have the best quality
– not impacting the quality, the great quality of water that Western Australia
has, and also making sure that we can accelerate our biodiversity and
rehabilitation efforts.
So, when you think about what happens next, the answer is we need to
come to an agreement with the Western Australian Government on what
we're doing in order to protect both of those things that then indicates where
we can mine the next set of tonnes, which then means we can have this
next round of permits that then buys us the certainty to be able to come
back to the normal bauxite grades again. Again, and sort of like with the
question that I had earlier, there's a lot of what ifs and a lot of questions
that sit in there. It is a process that is playing out right now. And we will
keep you updated as soon as we continue to hear what's happening next.
I appreciate the question, Alex.
Alex Hacking Thanks. It's a very helpful answer. And I do appreciate that it's a dynamic
situation and complex. So, thank you for the color.
Operator The next question comes from Lawson Winder with Bank of America
Securities. Please go ahead.
Lawson Winder Hi. Good evening, Roy and Molly. Two quick questions for me. First would
be in terms of your expectations for the CapEx ramp for 2023, which quarter
do you expect would be the heaviest level? And where do you expect Q2
2023 to be directionally versus Q1?
Molly Beerman So, Lawson, our fourth quarter is always the heaviest CapEx period and
we're still looking at $485 million for sustaining and $115 million for our

-- 20 of 23 --

20
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
return-seeking. I don't have the number handy between the quarters
before fourth.
Lawson Winder Would it be a gradual ramp-up like it has been in the past, so?
Molly Beerman Yes.
Lawson Winder Okay.
Molly Beerman Yeah. It'll follow the past gradual ramp-up.
Lawson Winder And then, I'm not sure I heard you mention it, but who is the third party that
referred the case to the EPA and what are their key concerns?
Roy Harvey So, we didn't specifically mention the third party, but it's a local NGO. The
concerns that they have are really – I did mention what the concerns were.
It's protecting the water quality. Because we are mining in areas that are
within the watershed for Perth, we need to make sure that we are
controlling erosion, that we're applying all these mitigating measures to
always protect water first and foremost, which is how we've always
approached this. But I think we need to make sure that we can provide
even more risk reduction in order to satisfy our regulators. The other piece,
of course, that they ask about is around biodiversity and how we are
rehabilitating in the Jarrah Forest. The Jarrah Forest is one of the most
beautiful places on the planet. It is an immense privilege for us to be able
to mine there.
I look back at our 60 years of operating in Western Australia and I'm very
proud of what we've been able to accomplish and that's on the science
side, as well as on the practical and pragmatic side of actually seeing that
restoration because it's been so long lived to see our restored habitat and
all the way from relatively new plantations, all the way to what is advanced
and developed new forests.
As you can imagine, our practices have improved year after year. We have
some super cool technologies that we've been able to start using really
over this last decade particularly. And we're very focused on making sure
that not only are we developing forest, but we're making sure that we
preserve all the biodiversity that was there after we finished rehabilitation.
So, we sort of measure the number of species and things along those lines.
And, in fact, we were one of the few Western Australian companies that, in
fact, has returned and received a certificate of completion for rehabilitation
that has been completed and then hand back over to the state. So, a great
legacy of stuff that we've been able to do. That's good, but we need to do
better and we need to accelerate. We need to make sure that we're also
rehabilitated very quickly, particularly in sensitive areas that obviously are
these places where we need to always be rehabilitating as quickly as we
possibly can.
So, all that to say those are really the two issues that they’ve really made
questions about. They happen to be aligned with the same things that we're
discussing with our regulators. So again, I think the answer here is that we

-- 21 of 23 --

21
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
need to make sure that we're delivering on what we've been requested,
which I'm very confident that we're doing. We just need to make sure that
we have those consensual discussions and the collaboration between the
government and Alcoa.
Lawson Winder Excellent. Thank you very much.
Roy Harvey Thank you, Lawson.
Operator And our last question is a follow-up from Lucas Pipes with B. Riley
Securities. Please go ahead.
Lucas Pipes Thanks very much for taking the follow-up and lots of great detail
throughout this call. So, thank you for that. The follow-up is on the LME
situation, Roy, that you mentioned earlier. Do you have a kind of timeline
in mind for a potential breaking point given the inflows of Russian metal in
London? Thank you very much for your perspective.
Roy Harvey Yeah, Lucas, it's always good to get these questions. It's hard to predict,
exactly. And I hate to think in too linear a fashion, but when we started out
this time last year, there was about five percent of inventories that were
Russian. We're now at 53 percent. I can't tell you when the market starts
to get more and more distorted, but at some point, the only thing left in LME
warehouses will be metal that is only consumed by a small group of non-
Western producers. We're seeing more and more of our customers that are
extremely sensitive to any Russian content, because if their products then
go to the U.S., they could have very significant tariffs placed on them,
because of the way that these tariffs were fashioned.
And so, to me, 53 percent, like I tried to be very clear in my remarks, is
already a point of significant warning that very quickly, we're going to get
to a point where the aluminum metal price, LME that's based off these
inventories is going to be based off metal that nobody wants. That's just
not a place that we want to be. It's just not sensible that we're seeing
curtailments through the rest of the world while Russia continues to operate
at full capacity. It just has no sense to me, which is why we believe the
sanctions are the best answer, number one, and number two, we think the
LME should delist Russian metal immediately.
Lucas Pipes I appreciate your color. Again, best of luck. Thank you.
Roy Harvey Thanks, Lucas.
Operator This concludes our question-and-answer session. I would like to turn the
conference over to Roy Harvey for closing remarks.
Roy Harvey Thank you, Vaishnavi, and thanks once again for everyone who joined our
call today. I've appreciated the questions and continued interest in Alcoa
and I also want to thank Molly for joining me for her first earnings call. I
know she'll be relieved that it's over, but it's also just a privilege and a
pleasure to have her here at my side.

-- 22 of 23 --

22
Alcoa Corporation
Wednesday, April 19, 2023, 5:00 PM Eastern
As we outlined in our presentation today, we're making progress every day
in accordance with our purpose, vision and values. We aim for continued
improvement in everything we do, and I truly have confidence in our teams
and their abilities. We know how to solve problems, that's been part of the
aluminum industry for the 25 years that I have been here. This includes the
challenges that we face today while continuing to work on our long-term
strategies on resolving Western Australia as a great example. We know the
future will bring even more importance to our products across the aluminum
value chain as the world works to decarbonize. That's why we've been so
focused on building an even stronger company and not sacrificing the work
that we're doing on our breakthrough technologies. And we intend to
remain resilient and ready, and running forward. I look forward to talk to
you again in July, when we'll share our second quarter results. In the
meantime, please be safe and once again, thanks for your time today.
Good night, everyone.
Operator The conference has now concluded. Thank you for attending today's
presentation. You may all now disconnect.

-- 23 of 23 --