TRANSCRIPT

Q3 2024 — Transcript

Q3 2024PDF · 21 pages245 KB
Alcoa Corporation
Third Quarter 2024 Earnings Presentation and
Conference Call
October 16, 2024, 5:00 PM Eastern
CORPORATE PARTICIPANTS
William Oplinger – President and Chief Executive Officer
Molly Beerman – Executive Vice President and Chief Financial Officer
Louis Langlois – Senior Vice President, Treasury and Capital Markets
OTHER PARTICIPANTS
Timna Tanners – Analyst, Wolfe Research LLC
Chris LaFemina – Analyst, B. Riley Securities, Inc.
Lucas Pipes – Analyst, B. Riley Securities, Inc.
Bill Peterson – Analyst, JPMorgan Securities LLC
Michael Dudas – Analyst, Vertical Research Partners LLC
Katja Jancic – Analyst, BMO Capital Markets Corp
John Tumazos – Analyst, John Tumazos Very Independent Research LLC
Carlos de Alba – Analyst, Morgan Stanley & Co. LLC
Lachlan Shaw – Analyst, UBS Securities Australia Ltd.

-- 1 of 21 --

1
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
PRESENTATION
Operator Good afternoon and welcome to the Alcoa Corporation Third Quarter 2024
Earnings Presentation and Conference Call. All participants will be in listen-
only mode. [Operator Instructions] After today's presentation, there will be
an opportunity to ask questions. [Operator Instructions] Please note this
event is being recorded.
I would now like to turn the conference over to Louis Langlois, Senior Vice
President of Treasury and Capital Markets. Please go ahead.
Louis Langlois Thank you, and good day everyone. I’m joined today by William Oplinger,
Alcoa Corporation President and Chief Executive Officer, and Molly
Beerman, Executive Vice President and Chief Financial Officer. We will
take your questions after comments by Bill and Molly.
As a reminder, today's discussion will contain forward-looking statements
relating to future events and expectations that are subject to various
assumptions and caveats. Factors that may cause the company's actual
results to differ materially from these statements are included in today's
presentation and in our SEC filings.
In addition, we have included some non-GAAP financial measures in this
presentation. For historical non-GAAP financial measures, reconciliations
to the most directly comparable GAAP financial measures can be found in
the appendix to today’s presentation. We have not presented quantitative
reconciliations of certain forward-looking non-GAAP financial measures for
reasons noted on this slide. Any reference in our discussion today to
EBITDA means Adjusted EBITDA.
Finally, as previously announced, the earnings press release and slide
presentation are available on our website.
Now let’s turn over the call to Bill.
William Oplinger Thank you, Louis, and welcome everyone, to our third quarter 2024
earnings conference call.
Alcoa had a strong third quarter. We maintained our fast pace of
execution on our strategic priorities while progressing operational
excellence with safety, stability, and continuous improvement. Underlying
the strength of our performance are positive market trends in both the
near and long term.
Let’s start with safety. First and foremost, we had no fatal or serious
injuries in the third quarter. I firmly believe that a strong safety culture
supports operational excellence. We have continued our positive trend in
both leading and lagging indicators, by focusing on the behaviors that
drive safety performance.

-- 2 of 21 --

2
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Operational stability is evidenced by our aluminum production increasing
for the eighth straight quarter, starting in the fourth quarter of 2022, with
year to date production records for our Mosjøen and Canadian smelters.
In fact, the Mosjøen smelter in Norway achieved its fourth consecutive
quarterly production record. We also steadily improved stability at the
Alumar smelter in Brazil, currently operating at nearly 80% capacity.
We are working through the approval process for the next major
Australian mine regions, Myara North and Holyoake, with the Western
Australia Environmental Protection Agency and the Australian Federal
bilateral assessment process.
Additionally, we have continued to deliver on our strategic actions during
the quarter.
We completed the acquisition of Alumina Limited on August 1st, and we
are already realizing benefits from this transaction on several fronts.
The acquisition resulted in increased economic exposure to the alumina
market, which is currently experiencing the highest pricing since 2018.
The transaction was accretive to third quarter results with the elimination
of net income attributable to noncontrolling interest after the closing date.
Alcoa also benefited from the absence of related cash distributions.
The consolidation of the tax structure of the two companies will result in
cash tax savings of approximately $100 million over next 12 to 18
months. The added flexibility in our financial decision making enabled us
to move quicker on the sale of our 25.1% stake in the Ma’aden joint
ventures, which we expect to close in the first half of 2025.
The Ma’aden transaction is consistent with our ongoing strategy to
optimize and simplify our current portfolio and business. It highlights
significant value for a non core asset. Additionally, the sale of the JV
interests allows Alcoa to avoid any future capital calls for their growth.
The transaction also provides us with enhanced financial visibility and
flexibility. With Ma’aden’s publicly traded shares, our shareholders will be
able to see the changing value this investment represents on our balance
sheet. If needed to avoid volatility, we may explore alternatives to hedge
the value of our investment within the parameters of our contractual lock
up periods.
Now I’ll turn it over to Molly, to take us through the financials.
Molly Beerman Thank you, Bill.
Revenue was flat sequentially at $2.9 billion. In the Alumina segment, third-
party revenue increased 9% on higher average realized third-party price,
partially offset by lower shipments. In the Aluminum segment, third-party
revenue decreased 5% primarily due to lower shipments.

-- 3 of 21 --

3
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Third quarter net income attributable to Alcoa was $90 million versus the
prior quarter of $20 million, with earnings per common share improving by
$0.27 to $0.38 per share.
On an adjusted basis, the net earnings attributable to Alcoa was $135
million, or $0.57 per share.
Adjusted EBITDA increased $130 million to $455 million.
Let’s look at the key drivers of EBITDA.
The third quarter Adjusted EBITDA increase was primarily due to higher
average realized third party prices for alumina, improved energy and raw
material costs, and lower other costs, only partially offset by lower metal
prices.
The Alumina segment increased $181 million primarily as higher alumina
prices more than offset higher production costs, raw material, energy, and
other costs.
The Aluminum segment decreased $53 million, primarily due to higher
alumina costs, lower metal prices, decreased shipments, and only partially
offset by raw material, energy and production cost improvements.
Outside the segments, other corporate cost decreased. Intersegment
eliminations were unfavorable in the quarter, which was expected, as the
higher average alumina price requires more inventory profit elimination.
Let’s look at cash movements within the third quarter on the next slide…
Year to date through September, capital expenditures and working capital
changes continue to be our largest uses of cash.
Within the third quarter working capital change, accounts receivable came
down, as lower aluminum sales prices outweighed the higher alumina sales
price impacts.
However, inventories in both segments rose, primarily due to timing of
shipments in Alumina.
Accounts Payable was lower due to timing of payments and impacts from
the Kwinana curtailment.
Overall, this resulted in an increase in working capital compared to the
second quarter.
Third quarter cash flows included approximately $85 million in
Restructuring payments, primarily related to the Kwinana curtailment.
We continue to progress our profitability improvement programs…
We have taken actions to deliver approximately $525 million of the $645
million savings target as of the end of the third quarter. Overall, the
improvements are apparent in the year to date, year over year bridge by
program or location. During the third quarter, we added $175 million to the
second quarter’s year to date progress of $350 million.

-- 4 of 21 --

4
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Through September 30, the Company overachieved its $310 million target
on raw materials with approximately $355 million in savings, and we expect
to expand those savings in the fourth quarter.
Within our productivity and competitiveness program, through September
30, we implemented actions contributing to approximately $45 million of
savings and expect to deliver the $100 million run rate target by the end of
the first quarter of 2025.
We have also progressed our portfolio improvements:
• To date, Warrick has achieved $45 million dollars of its $60 million
target. We are still awaiting further clarification from the U.S.
Treasury on the inclusion of direct materials in Section 45X of the
IRA program, which we estimate could be worth approximately $30
million.
• The Alumar smelter restart has achieved approximately $60 million
of its $75 million target, and is currently operating at nearly 80%
capacity.
• The Kwinana curtailment has been slow to deliver savings due to
high transition and holding costs, but we are still targeting $70
million in improvements on a run rate basis by the end of 2025.
Moving on to other key financial metrics…
The year to date return on equity turned positive to 0.6%.
Days working capital increased 4 days to 45 days sequentially, primarily
due to an increase in inventory days on timing of shipments.
Our third quarter dividend added $26 million to stockholder capital returns,
including newly issued shares for the acquisition of Alumina Limited.
Free cash flow less net noncontrolling interest distributions was nearly
neutral for the quarter, resulting in a cash balance of $1.3 billion.
As we look ahead to 2025, de-levering and repositioning debt to the
jurisdictions where cash is needed, will be a priority for us.
Turning to the outlook for the fourth quarter…

-- 5 of 21 --

5
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Our full year outlook has several adjustments:
We are increasing the outlook for alumina shipments to 12.9 to 13.1
million tonnes; that is an increase of approximately 200,000 tonnes. The
production outlook for alumina remains the same as most of the shipping
increase is related to trading tonnes where there is low margin.
While we expect Transformation expense to improve $10 million to $70
million, we also expect Other corporate expense to increase $20 million to
$160 million.
Depreciation expense is changing from $675 million to approximately
$655 million, primarily due to changes in capital project completion dates.
Return seeking capital is changing from $110 million to approximately
$135 million as we continue to consider several return seeking projects
with attractive rates of return, primarily related to production creep
projects and additional value add product capabilities.
Environmental and ARO payments are improving from $295 million to
approximately $265 million.
Regarding sequential changes for the fourth quarter:
• In the Alumina segment, we expect favorable impacts of
approximately $30 million from higher shipments and lower
production costs.
• In the Aluminum segment, we expect performance to be flat,
maintaining the strong performance from the third quarter.
• While the higher price of alumina will increase overall Alcoa
Adjusted EBITDA, alumina cost in the Aluminum segment is
expected to be unfavorable by $80 million.
• Beyond the standard sensitivity provided for intersegment profit
elimination, we expect an additional $30 million dollars of expense
in the fourth quarter due to the higher profit retained in inventory
related to changes in production costs and volumes.
Below EBITDA, we expect Other expenses to increase approximately $20
million related to equity losses in Ma’aden and an equity contribution to
ELYSIS.
Based on last week’s pricing, we expect fourth quarter operational tax
expense to approximate $120 to $130 million.
As the first full quarter since completing the Alumina Limited acquisition,
net income attributable to noncontrolling interest will be zero.
Now I’ll turn it back to Bill.

-- 6 of 21 --

6
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
William Oplinger Thanks Molly. Let’s start with an update on the markets.
The alumina price increased further in the third quarter to the highest
since 2018, as supply disruptions continued in a tight market.
So far this year, alumina buyers have faced force majeure in Queensland,
Australia, related to gas supply, force majeure in Jamaica after hurricane
impacts, and the curtailment of our Kwinana refinery in Australia. Recent
events in India have also raised questions of whether there could be even
further disruptions this year, but no impacts have been confirmed there
yet. Demand remains strong from continued smelter production growth
and relatively low alumina inventory levels at smelters, which is also
contributing to the tightness in the market.
Meanwhile, in the bauxite market, we have seen tightness in China due to
safety and environmental inspections in Northern China, along with
continued depletion of ore reserves. As a result, seaborne bauxite imports
there continue to grow this year.
Looking ahead to the alumina market for next year, for the market to
come back into balance, both the resolution of the recent disruptions, and
the ramp up of scheduled projects in Indonesia and India will be needed.
In aluminum, global demand is at record levels. Specifically in North
America and Europe, the packaging segment is recovering. The
transportation market overall has been steady with some slowing of
growth within the automotive sector. For building and construction, it has
been a challenging year, but rate cuts in Europe and in the U.S. are likely
to provide some support for a recovery in the future.
Global aluminum supply is growing, but with limited new projects in the
pipeline. China is approaching its 45 million metric tonne production
capacity cap, making any significant net supply growth from China
unlikely, and meaning supply growth instead will have to come from
outside of China. In addition, China announced that it is now including
aluminum in its national Emissions Trading Scheme, which sets national
carbon pricing. While we don’t expect to see immediate impacts from this
development, it does send a message that it is likely that the Chinese
primary aluminum industry, which makes up over half of global primary
aluminum production, will be subject to carbon emissions pricing,
increasing costs there in the future.
In summary, we believe the market environment remains positive for
alumina and aluminum. Alcoa is well positioned to benefit from being one
of the world’s largest bauxite and alumina producers, and from offering a
diversified portfolio of aluminum products that are used across several
end markets that are experiencing growth.

-- 7 of 21 --

7
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
The benefits of our significant alumina market exposure are starting to
become more apparent, not only in this pricing environment, but in
relation to the additional economic exposure gained through the Alumina
Limited acquisition.
Prior to the acquisition of Alumina Limited, Alcoa had economic exposure
through third party sales to only 2 million metric tonnes of production. We
had 60% of the approximately 10 million metric tonnes produced in total,
but used 4 million metric tonnes of that to supply our aluminum smelters.
Post acquisition, Alcoa has economic exposure to approximately 6 million
metric tonnes of production available for third party sales.
With our first quartile bauxite and alumina portfolio, we are in a very
strong position to take advantage of the near and long term market
fundamentals, as well as longer term strategic opportunities, like our
recently announced extension of the alumina supply contract with Alba.
The 10 year agreement provides up to 16.5 million metric tonnes of
smelter grade alumina to Alba. Our operations in Australia are well
positioned to serve Alba.
This contract also strengthens our position as the premier global alumina
supplier and enhances our ability to manage our long alumina position.
Turning to our Spain operations. Earlier this year, we announced a dual
path approach to address the challenging economics of the complex: the
launch of a sale process while also working to identify solutions for the
long term viability of the operations.
Following a robust sale process that included 60 potential investors, no
viable offer emerged. However, through the sale process, one party
emerged, the IGNIS Group, which was known to Alcoa through prior
dealings in Spain’s energy market.
Together, Alcoa and IGNIS developed an alternative through which both
organizations could leverage their individual expertise: our capabilities in
managing global aluminum operations, and IGNIS in leveraging their
energy market expertise to create value via market access and energy
management services.
We are working toward entering into a strategic cooperation agreement.
Under the terms of the agreement, IGNIS would become a 25% owner in
our Spanish operations. The owners would make initial investments of
€100 million: €75 million from Alcoa and €25 million from IGNIS.
Additionally, if required, up to €100 million would be funded by Alcoa with
a priority position in future cash returns. If additional funding is required, it
must be agreed by both partners and will be shared 75 percent by Alcoa
and 25 percent by IGNIS.

-- 8 of 21 --

8
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
However, this proposed partnership is conditional upon delivery of key
items by national and local Governments, Works Council and employees.
These include: Materially higher CO2 compensation, permitting of power
generation projects, support and approval for the residue storage area
capital project, and flexibility within the smelter Viability Agreement, such
as the ability to use restricted cash to meet operating needs until
competitive power is developed and provided under the signed PPAs.
We are now focusing on making the partnership a success with the
critical support from key stakeholders.
Our last strategic update is related to our Australian mine approvals…
We are currently progressing approvals along the timeline shown for the
next major Western Australian mine regions, Myara North and Holyoake,
through the WA EPA and Federal bilateral assessment process. It’s an
extensive process that started in 2020 and we are focused on receiving
Ministerial approval by early 2026. We anticipate mining in the new
regions will commence no earlier than 2027. Until then, we expect bauxite
quality will remain similar to recent grades.
The WA EPA recently set its indicative timeline for the next key step in
the process, the public comment period, for early 2025. We are
committed to working with the WA EPA and other stakeholders to achieve
the indicative timeline.
Alcoa has been and continues to engage with a range of stakeholders
regarding our current and future operations. We have community
engagement forums in place that provide an opportunity for two way
discussion between Alcoa and host community members. This includes
the recently established forum for the Dwellingup community, which is
near the future Holyoake mine region.
As we plan for future operations, we are assessing what conditions may
be applied through the approval process by examining our operations
closely as well as by learning from the experience of our peers operating
in the region.
In 2023, we accepted and incorporated new conditions addressing key
environmental factors that include enhanced protections for drinking
water and increased mining distances from reservoirs, avoidance of key
biodiversity areas, and accelerating forest rehabilitation. By incorporating
these conditions into our current operations, we believe they provide a
strong foundation for what may be recommended in the assessment.
Throughout all of these engagements, Alcoa’s goal is to be recognized as
a responsible miner and maintain the right to mine for long term
operations. We’re focused on modernizing the approvals framework for
bauxite mining in WA and securing certainty for our operations and all
stakeholders.

-- 9 of 21 --

9
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
As a company, we are proud of the progress we made in the third quarter
on multiple fronts.
Looking ahead, we will maintain a fast pace of execution on strategic
initiatives, improve productivity and stability across our operations, and
capitalize on positive market fundamentals to deliver value to our
stockholders.
It is shaping up to be an action packed year.
Operator, let’s start the question and answer session.
Operator We will now begin the question-and-answer session.
[Operator Instructions]
And our first question comes from Timna Tanners with Wolfe Research.
Please go ahead.
Timna Tanners Yes, thank you, and congratulations on all the progress.
William Oplinger Thanks, Timna.
Timna Tanners I've so many questions. Thanks. I guess I'll just ask about Spain. So, just
trying to understand. Have you got approvals or initial response from either
the union or the government? And assumedly, would you ramp-up
production to optimize profitability? What do they bring to the table? What's
your level of profitability at spot?
William Oplinger Yeah. Let me just address a few of those. What the partnership – first of
all, we're trying to achieve a partnership. We haven't finalized the
partnership yet, but our efforts on achieving a partnership are meant to
bring IGNIS' knowledge and expertise in the energy markets, combined
with our knowledge and expertise around aluminum.
And so around your question specifically, have we talked to the
stakeholders: the reason for the announcement today is to launch that
discussion with the stakeholders and to make sure that they understand
that we need cooperation to make the site viable. We specifically in the
announcement talked about a number of things: CO2 compensation,
permitting of power projects, the access to some of the restricted cash.
That will allow us to chart a path forward that makes that plant viable, but
it's conditional. The partnership is conditional on getting that cooperation,
and so that's what we'll be working on over the next couple of months.
Timna Tanners Okay. So, I know I ask a lot of questions, but I guess it would be helpful to
get a flavor on your confidence maybe on their approval and what the plan
B might be, I suppose, if you don't achieve those? And if you could
comment on the plans to run that more full utilization, that would be great,
too. Thanks.

-- 10 of 21 --

10
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
William Oplinger Yeah. If I step back and just address how we got here, we were going down
a dual path process, where we were trying to sell the asset and at the same
time trying to make it a viable asset. We went out to 60 potential buyers for
the asset, and there was not a viable offer for the entirety of the asset.
In that process, IGNIS emerged as a potential partner for us to essentially
combine their expertise and our expertise. In the partnership, they will be
making a €25 million contribution to the site. They will end up owning 25%
of the site, and we would hope to be able to work with the stakeholders so
that we can get the support that we need.
As far as my confidence, we're confident. We have made it this far. We've
had very good interaction with IGNIS, and we're confident that we can get
that – the partnership. Now, the question will be sitting down and making
sure that the stakeholders understand the need for the support that we're
looking for to ensure the solvency and the viability of the site.
Timna Tanners Thanks.
William Oplinger Thank you, Timna.
Operator And our next question comes from Chris LaFemina with Jefferies. Please
go ahead.
Chris LaFemina Hey. Thanks, operator. Yeah, just a follow-up question on the San Ciprián
situation. So, if my understanding is correct, you're committing up to €175
million of additional investment in the business. But is this sort of like it was
before, where that's the limit as to how far you'll go, or is it possible that
you will fund significantly more than that?
And I guess what I'm really getting at is, what is the endgame? I mean,
obviously, if it's a viable asset, well, then it could have a place within Alcoa.
But what if we go back to kind of lower price environment? How does that
play out for you? What are the options there?
William Oplinger The endgame here is to try to make it a viable asset, and the only way we
get to that endgame is that we have support from the unions and the
government. When you consider that €175 million that Alcoa would be
putting in, we will be looking for government support of the CO2
compensation of approximately $80 million. In addition to that, there is
restricted cash in the site, which is about $85 million, and we'd be looking
to access that to fund the operations. So, that's at least two of the things
that we need to get in order to get this a viable operation.
As we look forward, things can change in Europe, clearly. You've got CBAM
coming in, energy markets are changing fairly quickly. So, what we would
be looking to do is to try to get that support in order to make those
investments and have a site that's viable.
Anything you want to add, Molly?

-- 11 of 21 --

11
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Molly Beerman Just to add on the $80 million of the CO2 compensation, that actually
relates to the past. We did not receive our compensation for 2018 through
2021 when we were running the smelter, and so we've had claims against
the government. We'd like to have those lifted and have access to that $80
million since we ran and paid all of the employees.
William Oplinger And just to make it clear, to tie it all together, the €175 million, we would be
using the $80 million and the $85 million towards that contribution of €175
million.
Chris LaFemina That's helpful. Thank you. And sorry, second, Molly, just on the profitability
improvement program. Did you say that you're tracking ahead of some of
the cost reductions there? And does that imply that that $645 million target
might, ultimately, be conservative, or are we kind of sticking with that as
being the most likely outcome?
Molly Beerman Chris, we are ahead on the raw materials, and that was a year-over-year
target. So we're going to try to close off each piece of the program as we
accomplish it. We are working very diligently now on setting a really
aggressive 2025 plan. We recognize that any of these special programs
take a lot of time and energy. Alcoans are used to working toward an
aggressive plan, where we have every bit of savings and productivity
identified by person with delivery. So we will work on this program and close
it off as we accomplish each piece. And then, we're going to move forward
into 2025 with a really aggressive budget.
William Oplinger And if I could tag on to that comment, Molly, we're trying to change the
culture so that our company – the folks across the entirety of the company,
both within the plants and in our resource units, are focused very highly on
competitiveness. So, you've heard us talk about advancing
competitiveness and some of the targets that we've had. We're trying to
make sure that this is not a one-off program, that this becomes part of the
culture, where each plant, each resource unit is focused on increasing the
overall competitiveness of the plant in comparison to plants around the
world.
Chris LaFemina Great. Thank you. Good luck. Thanks.
William Oplinger Thank you.
Operator And our next question comes from Lucas Pipes with B. Riley Securities.
Please go ahead.
Lucas Pipes Thank you very much, operator, and I want to add my congratulations on
the progress across many fronts. I have one more question on San Ciprián.
Bill, in the past, the power component was always a challenge there, and I
wondered if you could maybe elaborate to what extent the potential
partnership would alleviate that previous chokepoint. Thank you very much.

-- 12 of 21 --

12
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
William Oplinger Thanks, Lucas. It's a great question, and the reason why it's a great
question is because power in Spain is still a problem. When you compare
power in Spain versus Germany and France, Spain is fundamentally
uncompetitive. And so, that's where we need to ensure that we get the
highest level of CO2 compensation available to us and any assistance we
can get in areas like transmission costs.
When you look at a smelter in France, for instance, they get the maximum
CO2 credit, they get the maximum assistance in transmission costs, which
allows a smelter in France, of all places, to be competitive. We need the
same type of thing in Spain. As far as what IGNIS can help us with is really
understanding underlying power markets, trying to help us with some of
those issues like CO2 compensation, transmission costs, and try to get us
a competitive power situation at least in the near-term while Europe works
through some of the things like CBAM and the energy situation there.
Lucas Pipes Thank you very much for that color. Very helpful. Bill, I'd like to ask you a
bit about the alumina markets. Obviously, very strong pricing dynamics,
lots of disruptions around the world and I wondered if you could maybe go
through some of the discrete pressure points on the supply side and share
your opinion on how quickly they might be resolved? And maybe also
separate from that, where else you might see constraints on alumina
medium term? Thank you very much.
William Oplinger Yes, alumina is acutely tight currently. I think on our chart, we showed
something like $650. I think alumina prices reached close to $700 today
and there is very little liquidity in the market for shipping alumina currently.
I'm sure that if I go through the list of disruptions, I'll probably miss one so
let me do it off the top of my head:
We curtailed the Kwinana facility earlier in the year. There is good strategic
rationale for curtailing it with high cost, high complexity refinery and we
made that happen safely in the first half of the year. Subsequent to that,
one of our competitors in Northern Australia had a pipeline issue. If you
look at their numbers year-over-year, they are recovering from that but are
still not back at 100% capacity.
One of our competitors in Jamaica had a storm roll through. They first said
there was no impact, subsequently declared force majeure, and so there
was an impact there. I believe that's been largely remedied. And just this
week, you probably heard some discussion, probably saw a Bloomberg
article about disruption around bauxite in Guinea. We don't know anything
more about that than what you're reading in the press, but that puts further
stress on the market.
As we look forward to 2025, our view would have been that 2025 would
come into balance at some point on Alumina. However, in order to come
into balance, a couple of things have to occur. Those disruptions need to
be cleared up and not recur. And secondly, we're going to need to see
growth in Indonesia and India.

-- 13 of 21 --

13
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
And I guess speaking of India, that was the one I missed. You probably all
saw at one of the competitors a run-off water storage pond that collapsed.
That may have had an impact on their production. So, in order for the
alumina market to come back into balance, we would need to see growth
in those two areas and our view is that alumina will stay tight through the
first half of next year.
Lucas Pipes Bill, I really appreciate all the color. To you and the team, continued best of
luck.
William Oplinger Thank you.
Operator And our next question comes from Bill Peterson with JP Morgan. Please
go ahead.
Bill Peterson Hi. Thanks for taking the questions and nice job on the quarterly execution.
I want to come back to San Ciprián and just maybe a little bit finer point.
So, I guess where alumina is today, how does this inform your refinery
restart? And I guess how does this tie in maybe potentially with the
negotiation with the unions and local governments? I guess on the
government side, what are you looking for? Is this about the commitments
to the renewable projects, the competitive PPAs? Just any sort of color you
can provide on those?
William Oplinger Let me answer the second part first and that'll give me time to forget the
first part. The second part, essentially what we're looking for, we laid out in
the press release and that is CO2 compensation, as Molly said, for past
production. That's about $80 million and we are looking for a permit for the
uplift of the RDA at San Ciprián. We need to uplift the RDA to 104 meters
and so we're looking to get that. On top of that, from the unions, we would
like to be able to access the restricted cash that's there to fund the
operating expenses as we go forward. Is there any that I'm missing?
Molly Beerman Just within the government discussions, we're also talking about the
permits. We do not have all the development permits. I should say the
suppliers under our PPAs don't have all the permits to develop.
William Oplinger Yeah. Good point. And as far as our thinking around ramping up the
refinery, we really need to get the permits to do that uplift to the 104 meters
in San Ciprián. And we'll be tracking those permits as they come in and
then once we have that, we'll make the determination then on whether we
want to increase production at San Ciprián.
Bill Peterson Yeah, thanks for that, Bill and Molly. Maybe the next one for Molly, on the
outlined, I guess, $120 million in remaining savings over the next, I guess,
12 to 15 months, sounds like you're going to come up with a 2025 plan. But
can you elaborate on where the remaining savings are coming from as well
as the cadence of the savings through the balance of next year?
Molly Beerman So, I mentioned that on raw materials, we've already overachieved. It will
actually add a little bit more in the fourth quarter there.

-- 14 of 21 --

14
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
On our productivity and competitiveness program, we are through $45
million of actions and that's to get the $100 million run rate and that's by
the end of the first quarter of 2025. Warrick, we're going after $60 million.
We've achieved about $45 million through the third quarter. We have zero
on the IRA, waiting that decision.
And then on the Alumar smelter, we're through $60 million of $75 million
and that will go into next year to get the rest of that. And then Kwinana is
the one where we are, I think, operating probably a bit behind target. We've
only captured $20 million of the $70 million. We're keeping the target. We
will go after that, but that will come more toward the end of 2025.
Bill Peterson Very helpful. Thank you, Molly.
Operator And our next question comes from Michael Dudas with Vertical Research.
Please go ahead.
Michael Dudas Good afternoon or evening, gentlemen. Molly.
William Oplinger Hey, Mike.
Michael Dudas Hey, Bill. Back to the alumina market, how do you see a balance on the
supply side, you talked about for 2025, but what about demand? I would
think it's near current prices given where aluminum is. How do you see that
for some of the higher cost smelters? Will there be some decisions on that
front that could certainly change things a little bit, maybe even on the
Congress side, tighten the aluminum market further?
William Oplinger So, as we're seeing demand today, demand actually has on the aluminum
side has been pretty strong. You've seen some restarts in Europe that
continue to drive the demand.
As far as whether alumina prices will drive demand cuts in aluminum, I can
really only speak for us and we would be looking at all of our smelters and
try to determine whether they can continue to be profitable at these levels
and how long those higher alumina costs will stick around. So, you know,
we have a pretty regular cadence of review of the profitability of our
marginal smelters and we go through that on a regular basis and we'll take
action if need be.
Michael Dudas Understood. Appreciate that. Thanks, Bill.
William Oplinger Thank you.
Operator And our next question comes from Katja Jancic with BMO Capital Markets.
Please go ahead.
Katja Jancic Hi. Thank you for taking my questions. Maybe starting on, given the
environment is very healthy right now, can you remind us how you're
thinking about your capital allocation, especially potentially returning
more to shareholders?

-- 15 of 21 --

15
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Molly Beerman Katja, our primary goal for early 2025 is to de-lever as well as to
reposition some of our debt to the jurisdictions that need cash. Our
adjusted net debt has gone a bit higher at $2.2 billion. We added
about $385 million this quarter with the completion of the Alumina
Limited acquisition. So, that will be our priority as we approach early
2025.
William Oplinger And Katja, if you look back over the last five years, I think one of the
greatest ways for us to release equity value is to pay down debt. We're a
bigger company today than we were a year ago. We're a more profitable
company today than we were a year ago, after the Alumina Limited
transaction, but I still believe that bringing down our debt levels is the best
way in the near-term to release equity value.
Katja Jancic And what would be the level you're looking to reach or you would be
comfortable at?
Molly Beerman We're looking at several options, Katja, but we're not ready to guide on that
yet.
Katja Jancic Okay. If I may, just one more. Given the strength in the alumina market and
the fact that there seems to be some durability expected in the prices, are
there any opportunities where you could, besides San Ciprián, increase
production or debottleneck on your side?
William Oplinger Short answer is largely no. I mean, we are working on debottlenecking in
Brazil, but that's taking some time. We constantly look at opportunities to
creep our sites and to try to generate additional tonnes, but really no large
step-outs that we could execute upon quickly to take advantage of these
higher prices.
Katja Jancic Okay. Thank you.
William Oplinger Thank you.
Operator And our next question comes from John Tumazos with Tumazos Very
Independent Research. Please go ahead.
John Tumazos Thank you for taking my question.
William Oplinger Hey, John.
John Tumazos Bill, I was playing with my excel spreadsheet and I plugged in $575 for the
fourth quarter alumina price and a $10 lower unit cost, and $625 million
popped out for EBITDA for the Alumina segment. And if something like that
happened, maybe the Aluminum metal segment with the transfer pricing
would fall toward $100 million. So, is it in the ballpark that we might see
$175 million gain in EBITDA in the fourth quarter, if the attorneys will let
you answer that question?
William Oplinger Hey, John. I'll take a swing at this, and Molly is much better at this. But
essentially, start with our third quarter. Take our sensitivities and apply our

-- 16 of 21 --

16
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
sensitivities. Put in your estimate of price that you think will last during the
fourth quarter, and then we give guidance around the strength of the fourth
quarter on some qualitative items.
So, what did we say qualitatively? We said alumina will be better by
about $30 million in the fourth quarter. I'm really happy about that. I
would like to see alumina get even better in 2025. But it's a very good
start. Aluminum is relatively flat on a fourth quarter to third quarter
basis. And then, I think Molly guided to a little bit of an impact of
change in inter-company profit elimination. With the rapid run up of prices
that we're seeing, sometimes our sensitivities don't always work perfectly.
And then, when we see that, we try to make sure that you can build it into
your model. So, once you've done all that, it spits out an EBITDA level. And
we'll let you make a determination whether you think it's realistic or not.
Thanks.
John Tumazos Bill, can I ask a second one?
William Oplinger Sure.
John Tumazos And I'm actually a little bit tongue-and-cheek and a little bit serious. I've sat
in three-hour geology seminars about the Nubian Shield or the Red Sea
basin, where the Saudi Arabian Peninsula is considered a very hot area for
gold and copper geology. Ivanhoe is exploring for copper; Barrick for gold
there. Should we view the $950 million of Ma'aden equity, and the majority
of their profits are phosphate, a long-term play on the phosphate market
and gold and copper exploration in the Nubian Shield? Or do you think it's
something that you might sell as soon as the holding period expires?
William Oplinger That's a great question, John, and let me just take the opportunity to give
you a little bit of background. We announced the transaction that we were
selling the 25.1% for $1.1 billion. The consideration is $150 million of cash
and $950 million of Ma'aden stock. That stock will be locked up on a lockup
period. That's a three-year, four-year to five-year staggered lockup period.
Since the time of that announcement, with the run up in the Ma'aden stock,
that transaction goes from being worth $1.1 billion to over $1.3 billion. So,
so far, we're pretty happy, but it's early days.
We did that transaction for two reasons. One, we wanted to simplify the
organizational structure. We did not think that the Street gave us much
value for the ownership of the 25.1%, and probably rightfully so. And then,
secondly, we wanted to be able to crystallize and highlight that value on
something that you can see on your screen on a daily basis to see how
much we own there. As far as whether we will sell those shares in years
three, four and five, we'll make that determination then. In the meantime,
we have a great relationship with Ma'aden. I personally have a great
relationship with many folks in the Kingdom, and we're super supportive of
them being successful on phosphate, copper, gold and aluminum.

-- 17 of 21 --

17
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
John Tumazos Whenever your production for metal is reported going forward, should we
add 228,000 tonnes for 2026 for the Spanish restart, and then deduct
175,000 tonnes because you sold the Ma'aden piece?
Molly Beerman John, I would wait till we get our partnership structure in place. Then, we'll
be able to give more guidance on what the restart ramp-up will look like.
In terms of Ma'aden, I have the off-take margin handy, but I don't have the
volume of tonnes. So, we have been taking off-take, and that will stop with
the completion of the transaction. That is not a huge margin to us. It's about
$6 million per quarter. But again, when we give our guidance in January on
the 2025 shipments and production, we will adjust at that point to remove
it.
John Tumazos Do you count it as production or not?
Molly Beerman Just shipments, I believe. Yeah, shipments.
John Tumazos Thank you.
William Oplinger Yeah. We don't count it as production. We count it as shipments because
we have an off-take with the joint venture that then gets sold onwards. So
it's in our shipments number, but not our production number.
John Tumazos Thank you for your patience with all my questions.
William Oplinger Thanks, John. Good to hear from you.
Operator And our next question comes from Carlos De Alba with Morgan Stanley.
Please go ahead.
Carlos DeAlba Yeah. Thank you very much, Bill and Molly. On San Ciprián, is there
a new timetable or a timetable for you to complete the discussions
with the government and the union in order for you to determine
whether you go ahead with this agreement that you are trying to
close? Just would like to get a little bit of sense of time as to how
much longer can this negotiation take before you are ready to really
turn the page or continue operating the San Ciprián asset.
William Oplinger Not a significant change to the timetable that we've lined out before.
The entities will run out of cash, we believe, somewhere around the
end of the year. Potentially, that could go a little bit further into 2025,
depending on what market conditions are. So, we're essentially
pushing as hard as we can, as quickly as we can to ensure that we
get the right level of cooperation from the various stakeholders and
get the partnership consummated.

-- 18 of 21 --

18
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
Carlos DeAlba Okay. And just if the companies run out of cash at that point in time, do you
basically file for bankruptcy or stop – you close shop? Is that what will
happen?
William Oplinger We're really focused on trying to make sure that that doesn't happen,
Carlos. But essentially, the entity is technically insolvent at that point.
And so, as we've said before, some hard decisions will have to be
made. What we're trying to do is avoid that.
Carlos DeAlba Okay. All right. Thanks. And just on CapEx, is this the second quarter in a
row that CapEx goes up or return-seeking CapEx increases? Any – not
huge amounts, but anyway increases – any details or any color as to how
much incremental either volumes or EBITDA can we expect from this
project, these additional projects?
Molly Beerman Yeah. Carlos, we don't have those figures handy. I don't think you'll find it
to be notable, though, from this current set. These are a series of smaller
projects that we're improving now.
Carlos DeAlba All right. Okay. Thank you very much. All the best.
William Oplinger Thank you.
Operator And our next question comes from Lachlan Shaw with UBS. Please go
ahead.
Lachlan Shaw Afternoon, Bill and Molly. Thanks for your time. Just one question
from me. So, just on WA and the mine approval process there. I'm
just interested, I suppose, how you think about that whole process
and the scenarios potentially ahead of you given the experience of
your peer there and the conditional approvals that sort of came
through for them. I mean, how do you think about what those
scenarios might look like in the context of the environmental
authorities in Australia generally pushing for more stringent
conditions? Thank you.
William Oplinger Lachlan, thanks for the question. We're continuing to advance the mine
approvals for both Myara North and Holyoake. That process started in 2020
and we're focused on receiving our approvals by early 2026 and we're
anticipating that mining in the new regions will commence no earlier than
2027.
Recently, the WA EPA set the timeline for the next major step in the
approval process, and that's the public comment period. That will occur in
the first quarter of 2025. The same time, we continue to work on our annual
approval from the WA state government for a rolling five-year mine plan.
So, we continue to make good progress. We're committed, very committed
to making sure that we work collaboratively – I can't say that word –
collaboratively with the WA EPA and the other stakeholders. So, we think
we're making really good progress there.

-- 19 of 21 --

19
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
As far as your question around our neighbors in WA, South32, we
have looked at some of their conditions and we acknowledge that
there's some similarities between the activities between the two
companies. But we continue to work through a review of their
process and we think that we will learn a lot through that process.
And we think we're actually in pretty good shape. So, I don't know if
there's anything you want to add to that, Molly.
Molly Beerman I'd just add that remember, last year, when we were going through the
approvals process of our annual mine plan, we adopted a whole series of
new mining requirements. So, many of the conditions that you see being
added to South32 now, we've already done that.
So, we did go through their whole list. We looked at them, the
majority we had either already built-in to our current mine plans or
had them incorporated in our new mine plans. And some of those
that were different are simply because we're mining in different
areas. Some of the other South32, it's important to recognize that
some of their cost increases are related to their carbon management.
William Oplinger Yeah.
Molly Beerman We are running natural gas, so we do not face the same kind of cost
challenges. The safeguard mechanism that'll be running in Australia
is based on the industry standard and if you look at our Pinjarra
Refinery, for example, we're already at the industry best. So, we have
a different cost profile there as well.
Lachlan Shaw That's great color. Thanks again.
William Oplinger Thanks, Lachlan.
Operator And our next question is a follow-up from Timna Tanners of Wolfe
Research. Please go ahead.
William Oplinger Hi, Timna.
Timna Tanners Yeah. Hey, thanks very much. I just wanted to follow-up on the capital
allocation line of questioning because I know that Molly, in the prepared
remarks, noted some ability to continue to pursue perhaps some value-add
or additional projects. And just back of the envelope, higher alumina prices
continuing, these commodity prices, obviously paying down debt's great
use of cash, I get it. But anything else you can elaborate on regarding
further opportunities if indeed you have greater cash and cash generation
into next year?
Molly Beerman Timna we will certainly look at excess cash and we will put it through our
capital allocation framework. So, we will look at returns to shareholders,
we'll look at other growth opportunities, and we'll also look at additional
portfolio actions. But we will wait to see how the cash is coming in through

-- 20 of 21 --

20
Alcoa Corporation
Wednesday, October 16, 2024, 5:00 PM Eastern
the rest of this year and into early next year along with those de-levering
plans that I mentioned.
William Oplinger It is important to remember that at the beginning of the year, we issued
$750 million of debt. We also took on an additional roughly $350 million
debt in the Alumina transaction. As I said earlier, we are a bigger company,
we should be a better company, but in the near-term, we think there's a lot
of value, equity value created by de-levering.
Timna Tanners Okay. Fair enough. Thank you.
William Oplinger Thanks.
Operator That concludes our question-and-answer session. I would like to turn the
conference back over to Mr. Oplinger for closing remarks.
William Oplinger Thank you for joining our call. Molly and I look forward to sharing further
progress when we speak again in January. That concludes our call.
Operator The conference has now concluded. Thank you for attending today's
presentation. You may now disconnect.

-- 21 of 21 --